DE SOTO COUNTY · ROAD PROJECTS · VERIFIED THROUGH SEPTEMBER 29, 2026
Maintained, source-backed road project tracker — not a standard article. Evidence cutoff: September 29, 2026.
DeSoto County Road Projects: Getwell Road, I-55, Highway 305 & Current Status
DeSoto County's February 2026 four-year road plan names 15 projects and a separate list of nine longer-range priorities. They include county, city and MDOT roads; appearing on the list does not mean a project has construction money or an awarded contract. Getwell Road has several distinct sections: Southaven's Church Road–Star Landing widening is completed, while other sections have different design, right-of-way and planning records. A $44 million federal INFRA award was announced September 28 for an MDOT I-55/I-69 corridor, but it does not fund every interstate phase in the county plan. Highway 305's proposed widening must also be separated from maintenance work and proposed legislation. Use the segment and phase records below to see what is established and what remains unknown. [S01, S02, S03, S06, S08, S10]
Statuses describe the cited record as of the baseline, not live traffic or a guarantee that a projected date will be met. "No award located" describes this investigation, not proof that no award exists.
Evidence Rules
- · County priority ≠ funding
- · Estimated cost ≠ appropriation
- · Design/ROW programming ≠ construction funding
- · Proposed letting ≠ contract award
- · Award ≠ notice to proceed
- · NTP ≠ observed physical work
- · Nearby work ≠ the same contract
- · Maintenance ≠ widening
- · One Getwell section ≠ the whole corridor
- · County plan entry ≠ county-controlled project
- · Federal award for one corridor ≠ funding for every phase
- · Projected completion ≠ contractual or actual completion
Current Status Dashboard
WHAT IS COMPLETED?
COMPLETEDGW-01 Church–Star Landing widening; city record reports completion. Exact acceptance date unverified.
WHAT IS IN DESIGN?
DESIGNGW-02 and GW-04 have TIP design phases programmed; GW-03 design task historically approved. "Design complete" for Starlanding 1/4 is only a county plan label.
WHAT IS IN ROW?
ROWGW-03 county plan says "In ROW"; GW-02/04 have FY2027 ROW programmed; GW-05 plan says ROW. No acquisition completion inferred.
WHAT HAS PROGRAMMED FUNDING?
PROGRAMMEDGW-02/GW-04 design and ROW; RP-01 ROW; GW-05 signal construction grouping. Report phase and source.
WHAT HAS A VERIFIED CONSTRUCTION AWARD?
AWARDEDGW-01 historical low bid reported; no prospective Getwell widening award established here.
WHAT IS UNDER CONSTRUCTION?
UNDER CONSTRUCTIONNo prospective Getwell widening section established as physically under construction. Do not claim none anywhere countywide without checking each agency.
WHAT IS LONGER RANGE?
LONGER RANGENine separately labeled county priorities; GW-02/04 also have current programmed preconstruction phases.
Getwell Road Widening: Which Section Is Which?
Pleasant Hill–Lester and Pleasant Hill–I-269 are not the same Getwell Road project. The first runs north from Pleasant Hill to Lester (GW-03); the second runs south from Pleasant Hill toward I-269 (GW-04). Star Landing–Lester (GW-02) is another northern section. Southaven's Church–Star Landing widening (GW-01) is an older completed project. The intersection at Pleasant Hill (GW-05) and Central Parkway–Church trail (GW-06) have their own scopes.
GW-01: Church Road → Star Landing Road
Project: MS-LSTP-2014-01
Lead: Southaven
Two to five lanes; median, College signal; city reported $14,060,127 low bid, $7,887,061 federal allocation, March 1, 2023 actual stated construction start; later city record lists completion.
Actual start: 2023-03-01
Exact acceptance date null; don't reuse old start for GW-02/03/04. County's $875,000 assistance for Star Landing intersection is not another whole-road cost.
Sources: S03, S06
GW-02: Star Landing Road → Lester Road
Project: MS-STBG-2026-02
Lead: DeSoto County
TIP 0.94 mi, 2→4 divided lanes. DeSoto County lead, Southaven geography/partner.
- Estimated total:
- $12,792,712
- Design FY2026:
- $808,082 ($646,466 federal / $161,616 local)
- ROW FY2027:
- $559,193 ($447,355 federal / $111,838 local)
Length: 0.94 mile · Lanes: 2 → 4
Construction phase not shown in adopted TIP; no construction award/start established. Estimated total ≠ construction funding.
Sources: S01, S02
GW-03: Lester Road → Pleasant Hill Road
Lead: DeSoto County
About 0.5 mi, 2→5 lanes. Waggoner design task approved in 2021.
- Estimated total:
- $5.5–6.5m
Length: 0.5 mile · Lanes: 2 → 5
ROW complete null; bond balance/current eligible scope null; construction funding/award/NTP/work/contractor/completion null. Plan "in ROW" is not ROW completion.
Sources: S01, S04, S05
GW-04: Pleasant Hill Road → I-269
Project: MS-STBG-2026-01
Lead: DeSoto County
TIP: 0.95 mi, 2→5 lanes. DeSoto County lead, Hernando geography/partner.
- TIP estimated total:
- $10,752,318
- County estimate:
- $10–12m
- Design FY2026:
- $646,466 ($517,173 federal / $129,293 local)
- ROW FY2027:
- $559,193 ($447,355 federal / $111,838 local)
SOURCE DISCREPANCY — NOT YET RECONCILED
County plan: approximately 0.5 mile
MPO TIP: 0.95 mile
Length: 0.95 mile · Lanes: 2 → 5
County longer-range plan says about 0.5 mi: unresolved length conflict. Construction phase not shown in adopted TIP. June 2026 agenda references MOA; execution unverified.
Sources: S01, S02, S11
GW-05: Getwell Road × Pleasant Hill Road (Intersection)
Lead: DeSoto County
Separate signal and turn-lane intersection project. County plan ROW, estimate $2–3m. MPO grouping lists $3,840,845 federal construction programming.
- County estimate:
- $2–3m
- MPO federal:
- $3,840,845 federal construction programming
May 2025 minutes reported NTP received and anticipated summer 2026 MDOT start; April 2026 agenda referenced PS&E. Verify NTP instrument, what work it covers, contract award and actual physical start; do not label under construction.
Sources: S01, S02, S12
GW-06: Central Parkway → Church Road (Multi-Use Trail)
Lead: Southaven
Southaven multi-use trail, NOT widening. Easements acquired. Approximately $800k projected after bidding.
- Bidding:
- November 2026 — PROJECTED
- Construction:
- Spring 2027 — PROJECTED
- Completion:
- July 2027 — PROJECTED
Contractor/award/start/actual completion null; excluded from widening totals. Never include GW-06 in Getwell widening totals.
Sources: S07
Getwell Corridor Schematic
SCHEMATIC — NOT TO SCALE
North to south. GW-06 (trail) shown separately — not a widening segment.
I-55/I-69 Widening Phases
Phase 1: Goodman → Church
ESTIMATED PROJECT COST: $156m
4 → 8 lanes (county plan)
Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.
Phase 2: Church → I-269
ESTIMATED PROJECT COST: $168m
4 → 8 lanes (county plan)
Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.
Phase 3: Starlanding interchange
ESTIMATED PROJECT COST: $45m
4 → 8 lanes (county plan)
Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.
Phase 4: Commerce interchange → Starlanding
ESTIMATED PROJECT COST: $50m
4 → 6 lanes plus interchange changes (county plan)
Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.
September 28, 2026 · $44 MILLION · INFRA FEDERAL AWARD ANNOUNCED
Lead: MDOT
Corridor: Church Road → approximately one mile north of SR 302/Goodman Road
Lane description: 4 → 10 lanes per Sep 28 award source
SOURCE DISCREPANCY — NOT YET RECONCILED
February county plan: 4 → 8 lanes. September award announcement: 4 → 10 lanes.
Attribute each. Do not reconcile them yourself.
This is a specific corridor award. It does NOT establish funding for all four I-55 phases. Do not automatically subtract $44m from the $156m Phase 1 estimate.
PROPOSED LETTING — SUBJECT TO CHANGE
MDOT proposed letting: February 2027
Project: NH-0055-04(077)V21 / 100222/303000
Contractor: UNKNOWN
Contract award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
Never: "Construction starts February 2027." A letting is a procurement milestone, not a construction start date.
MDOT's I-55/I-69 mill and overlay between I-269 and Church is pavement rehabilitation, not proof that the four widening phases began. [S16]
Highway 305
Three separate records. Never merge widening, legislative proposals, and maintenance.
H305-W: WIDENING
Corridor: Church → Byhalia
Lead: MDOT
Status: County priority
Funding: NOT ESTABLISHED
County plan alone does not establish construction funding.
Sources: S01
H305-BILL: LEGISLATIVE PROPOSAL
Corridor: Church → I-269
Lead: Mississippi Legislature
Bill: SB3324 introduced text
Status: PROPOSED APPROPRIATION
Funding: NOT ESTABLISHED — introduced language is not funding
Do not call funded. Enactment not established from the cited primary bill text.
Sources: S09
H305-M: MAINTENANCE
Corridor: Approximately 1.6 miles near Tennessee line
Lead: MDOT
Work: Scrub seal / microsurfacing
Letting: April 30, 2025
Status: MAINTENANCE
Never present maintenance as widening.
Sources: S17
Project Inventory
All 15 four-year and 9 longer-range source records. Use filters to narrow by corridor, agency, type, or plan list.
24 of 24 records
Starlanding Road (Segment 3)
Starlanding Road
Cumberland Road → Swinnea Road
Lead: DeSoto County
Type: ROAD WIDENING
Plan status: ROW
Estimate: $9–12m
Verified: 2026-09-29
Getwell/Pleasant Hill intersection
Getwell Road
Getwell Road → Pleasant Hill Road
Lead: DeSoto County
Type: INTERSECTION SIGNAL
Plan status: ROW
Estimate: $2–3m
Verified: 2026-09-29
Getwell (Pleasant Hill to Lester)
Getwell Road
Pleasant Hill Road → Lester Road
Lead: DeSoto County
Type: ROAD WIDENING
Plan status: IN ROW
Estimate: $5.5–6.5m
Verified: 2026-09-29
Ingrams Mill Road Bridge
Ingrams Mill Road
Lead: UNKNOWN
Type: BRIDGE REPLACEMENT
Plan status: ROW
Estimate: $2–3m
Verified: 2026-09-29
I-55 Phase 1
I-55/I-69
Goodman Road → Church Road
Lead: MDOT
Type: INTERSTATE WIDENING
Plan status: MDOT PHASE 1
Estimate: $156m
Verified: 2026-09-29
I-55 Phase 2
I-55/I-69
Church Road → I-269
Lead: MDOT
Type: INTERSTATE WIDENING
Plan status: MDOT PHASE 2
Estimate: $168m
Verified: 2026-09-29
I-55 Phase 3
I-55/I-69
Starlanding interchange → Starlanding interchange
Lead: MDOT
Type: INTERCHANGE
Plan status: MDOT PHASE 3
Estimate: $45m
Verified: 2026-09-29
I-55 Phase 4
I-55/I-69
Commerce interchange → Starlanding
Lead: MDOT
Type: INTERSTATE INTERCHANGE
Plan status: MDOT PHASE 4
Estimate: $50m
Verified: 2026-09-29
U.S. 51
U.S. 51
Venture Drive → Green T Road
Lead: MDOT
Type: STATE HIGHWAY WIDENING
Plan status: MDOT
Estimate: Not established
Verified: 2026-09-29
Highway 305
Highway 305
Church Road → Byhalia Road
Lead: MDOT
Type: STATE HIGHWAY WIDENING
Plan status: MDOT
Estimate: Not established
Verified: 2026-09-29
Holly Springs–Jaybird
Holly Springs Road
Holly Springs Road → Jaybird Road
Lead: UNKNOWN
Type: ROUNDABOUT
Plan status: ROW
Estimate: $3m
Verified: 2026-09-29
Hacks Cross Road
Hacks Cross Road
College Road → Bethel Park
Lead: UNKNOWN
Type: ROAD WIDENING
Plan status: ROW
Estimate: $7.2m
Verified: 2026-09-29
Byhalia–Jaybird
Byhalia Road
Byhalia Road → Jaybird Road
Lead: UNKNOWN
Type: ROUNDABOUT
Plan status: PLANNING
Estimate: $4m
Verified: 2026-09-29
Holly Springs/Nail/Nesbit overlay
Holly Springs/Nail/Nesbit
Lead: DeSoto County
Type: OVERLAY
Plan status: DESIGN
Estimate: $3.4m
Verified: 2026-09-29
Malone Road Bridge
Malone Road
Lead: UNKNOWN
Type: BRIDGE REPLACEMENT
Plan status: DESIGN
Estimate: $925k
Verified: 2026-09-29
Craft widening, Freedom–I-269
Craft Road
Freedom Road → I-269
Lead: UNKNOWN
Type: ROAD WIDENING
Plan status: 5–15 YEAR PRIORITY
Estimate: null
Verified: 2026-09-29
Pleasant Hill/McIngvale
Pleasant Hill Road
Pleasant Hill Road → McIngvale Road
Lead: UNKNOWN
Type: INTERSECTION SIGNAL OR ROUNDABOUT
Plan status: 5–15 YEAR PRIORITY
Estimate: TBD
Verified: 2026-09-29
Laughter/Byhalia
Laughter/Byhalia
Laughter Road → Byhalia Road
Lead: UNKNOWN
Type: INTERSECTION CULVERT
Plan status: 5–15 YEAR PRIORITY
Estimate: TBD
Verified: 2026-09-29
Byhalia–Jaybird (longer range)
Byhalia Road
Byhalia Road → Jaybird Road
Lead: UNKNOWN
Type: ROUNDABOUT
Plan status: 5–15 YEAR PRIORITY
Estimate: $4m
Verified: 2026-09-29
Craft alignment, College–Bethel
Craft Road
College Road → Bethel Road
Lead: UNKNOWN
Type: NEW ROAD
Plan status: 5–15 YEAR PRIORITY
Estimate: TBD
Verified: 2026-09-29
Starlanding Segment 4
Starlanding Road
Baptist Road → Getwell Road
Lead: DeSoto County
Type: ROAD RECONSTRUCTION
Plan status: 5–15 YEAR PRIORITY
Estimate: $10–14m
Verified: 2026-09-29
Starlanding Segment 1
Starlanding Road
Tulane Road → Railroad
Lead: DeSoto County
Type: ROAD RECONSTRUCTION
Plan status: 5–15 YEAR PRIORITY
Estimate: TBD
Verified: 2026-09-29
Getwell Pleasant Hill–I-269 (longer range)
Getwell Road
Pleasant Hill Road → I-269
Lead: DeSoto County
Type: ROAD WIDENING
Plan status: 5–15 YEAR PRIORITY
Estimate: $10–12m
Verified: 2026-09-29
Getwell Star Landing–Lester (longer range)
Getwell Road
Star Landing Road → Lester Road
Lead: DeSoto County
Type: ROAD WIDENING
Plan status: 5–15 YEAR PRIORITY
Estimate: $12–14m
Verified: 2026-09-29
Funding, Cost, ROW and Procurement
NON-ADDITIVE LEDGER
These numbers represent different categories and stages and cannot responsibly be combined into one total-spending figure. Never calculate a site-wide "DeSoto County is spending $X million on roads."
Each project shows four distinct fields: ESTIMATED TOTAL PROJECT COST, PROGRAMMED PHASE FUNDING, CONSTRUCTION CONTRACT AWARD, and SPENT TO DATE. Missing amounts read "Not established in reviewed records," not "$0."
Funding Records
$12,792,712
Project: GW-02 · Phase: whole project
Source: MPO TIP
Not construction funding
$808,082
Project: GW-02 · Phase: design FY2026
Source: MPO STBG-M-MS/local
Not obligated/spent; federal $646,466, local $161,616
$559,193
Project: GW-02 · Phase: ROW FY2027
Source: MPO STBG-M-MS/local
Not acquired; federal $447,355, local $111,838
$10,752,318
Project: GW-04 · Phase: whole project
Source: MPO TIP
Not construction funding
$646,466
Project: GW-04 · Phase: design FY2026
Source: MPO STBG-M-MS/local
Federal $517,173, local $129,293
$559,193
Project: GW-04 · Phase: ROW FY2027
Source: MPO STBG-M-MS/local
Federal $447,355, local $111,838
$5.5–6.5m
Project: GW-03 · Phase: whole project
Source: County plan
Range; not appropriated
$1.5m
Project: GW-03 · Phase: historical bond account
Source: Mississippi state bond
Current balance, exact segment allocation, obligations and spent amount unknown
$3,840,845
Project: GW-05 · Phase: signal construction grouping
Source: MPO STBG federal
Not the final contract amount
$156m
Project: RP-05 · Phase: plan phase 1 total
Source: County plan
Not construction award or full funding
$44m
Project: I55-AWARD-01 · Phase: Church to north of SR302 corridor
Source: INFRA
Announced award; not every phase, obligated/spent/contract amount unknown
$14,060,127
Project: GW-01 · Phase: historical widening low bid
Source: Southaven report
Reported lowest bid; not later prospective sections
$7,887,061
Project: GW-01 · Phase: historical federal allocation
Source: Federal via MPO/MDOT
Reported allocation; not spending proof
$2,000,001
Project: RP-01 · Phase: ROW
Source: Federal earmark/local
Federal $1,600,001 and local $400,000; not whole project cost
~$800k
Project: GW-06 · Phase: trail whole project
Source: Southaven
Approximate city projection, not bid amount
ROW / Utility Status
GW-02
ROW: ROW PROGRAMMED
Utility: UNKNOWN
Sources: S02
GW-03
ROW: ROW ACTIVE PER COUNTY PLAN
Utility: UNKNOWN
Sources: S01
GW-04
ROW: ROW PROGRAMMED
Utility: UNKNOWN
Sources: S02
GW-05
ROW: ROW PER COUNTY PLAN
Utility: UNKNOWN
Sources: S01
GW-06
ROW: EASEMENTS ACQUIRED
Utility: UNKNOWN
Sources: S07
RP-01
ROW: ROW PROGRAMMED
Utility: UNKNOWN
Sources: S01, S02
Procurement / Construction Status
GW-02
Bid stage: NOT LOCATED
Award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
GW-03
Bid stage: NOT LOCATED
Award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
GW-04
Bid stage: NOT LOCATED
Award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
GW-05
Bid stage: NOT LOCATED
Award: NOT VERIFIED
NTP: REPORTED IN 2025 MINUTES
Physical construction: NOT VERIFIED
GW-06
Bid stage: PROJECTED NOV 2026
Award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
RP-05
Bid stage: PROPOSED FEB 2027
Award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
RP-14
Bid stage: POSSIBLE MATCH ADVERTISED
Award: NOT LOCATED
NTP: NOT LOCATED
Physical construction: NOT VERIFIED
Who Is Responsible for DeSoto County Road Projects?
A road being located in DeSoto County does not mean DeSoto County controls the project.
DeSoto County
County plans/priorities and lead on TIP GW-02, GW-04 and Starlanding Segment 3; county Getwell GW-03 and intersection GW-05. Partners may share costs.
MDOT
Lead for interstate, U.S. 51 and state Highway 305 entries; publishes state schedules and lettings.
Southaven
Lead for completed GW-01 and separate GW-06 trail; partner/geography on GW-02.
Olive Branch
Associated with Hacks Cross county collaboration and leads other distinct MPO projects, including Pleasant Hill Road widening.
Hernando
Geography/partner reflected in MPO for GW-04; MPO lists DeSoto County as lead.
Horn Lake
Municipality with its own roads and MPO projects; no sole-lead entry in the 15-row county list established.
Memphis MPO
Programs eligible transportation phases and federal allocations; does not thereby become the road owner or construction contractor.
Federal programs
INFRA award and TIP funds apply to specified projects/phases, not every project in the county.
Project Timeline
Solid markers = documented past events. Outlined markers = planned/projected events. Do not change planned milestones to completed merely because their projected date passes.
RECORD DATE
2021-01-19
County approved design task for Lester–Pleasant Hill
Source: S04
RECORD DATE
2022-04-18
County recorded $1.5m state bond accounting for Getwell/Pleasant Hill
Source: S05
ACTUAL START
2023-03-01
Southaven stated start of Church–Star Landing widening
Source: S03
ACTUAL COMPLETION
Date not established
Later Southaven meeting record lists project completion; exact date not established
Source: S06
RECORD DATE
2025-05-22
County minutes reported NTP received and anticipated summer 2026 MDOT start; physical start unverified
Source: S12
RECORD DATE
2026-02-18
County four-year and longer-range plan dated
Source: S01
PROGRAM YEAR
2026
Adopted TIP programs design in FY2026, ROW in FY2027; no construction phase shown
Source: S02
RECORD DATE
2026-06-19
County agenda references I-269–Pleasant Hill MOA approval item; execution unverified
Source: S11
RECORD DATE
2026-09-15
Southaven reports easements acquired and projected bid/start/completion
Source: S07
RECORD DATE
2026-09-28
$44m INFRA award announced for specified MDOT corridor
Source: S08
PROPOSED LETTING
2027-02
MDOT proposed reconstruction/widening letting; subject to change
Source: S10
BID DATE
2026-11
Southaven projected trail bidding, not advertisement
Source: S07
PROJECTED COMPLETION
2027-07
Southaven projected trail completion, not contractual date
Source: S07
Frequently Asked Questions
What road projects are planned in DeSoto County?
The county's February 2026 plan lists 15 four-year entries and nine separate longer-range priorities. They range from Getwell and Starlanding to MDOT highways and bridge, intersection and overlay work. A plan entry alone does not confirm funding or construction. [S01]
What roads are currently being widened?
The reviewed records establish a completed Getwell widening and future/programmed sections, plus an MDOT interstate widening proposal and federal award. They do not establish that the prospective Getwell sections are physically under construction. This tracker is not a live roadwork feed. [S02, S06, S08]
What is happening with Getwell Road?
Several separate sections have different agencies and stages. Church–Star Landing is completed; Star Landing–Lester and Pleasant Hill–I-269 have programmed design/ROW; the county plan says Lester–Pleasant Hill is in ROW. [S01, S02, S06]
How many Getwell projects are tracked?
Six records: four consecutive widening sections, a separate Pleasant Hill intersection, and a separate trail. Only the first four are widening sections. [S01, S02, S03, S07]
Is Getwell Road being widened now?
No prospective widening section's physical construction start is established by the reviewed records. The completed Church–Star Landing work is often present in older results. [S03, S06]
What is happening between Star Landing and Lester?
MPO MS-STBG-2026-02 programs design in FY2026 and ROW in FY2027 for about 0.94 mile; it does not show construction programming in the adopted TIP. [S02]
What is happening between Lester and Pleasant Hill?
The county's four-year plan labels approximately 0.5 mile "In ROW." A design task and historical state bond activity are documented, but ROW completion and construction award are unverified. [S01, S04, S05]
What is happening between Pleasant Hill and I-269?
MPO MS-STBG-2026-01 programs design and ROW, not construction; its 0.95-mile length differs from the county list's approximately 0.5 mile. [S01, S02]
Are Pleasant Hill–Lester and Pleasant Hill–I-269 the same project?
No. They meet at Pleasant Hill but extend in opposite directions and have different records. [S01, S02]
When will Getwell construction start?
There is no verified construction start date for GW-02, GW-03 or GW-04. The March 2023 start belonged to the now completed Southaven section. [S02, S03]
Is Getwell widening fully funded?
The TIP programs design/ROW for GW-02 and GW-04; their estimated total costs are not construction appropriations. Full construction funding is not established in these records. [S02]
What is happening at Getwell and Pleasant Hill?
A separate county signal and turn-lane project appears in the plan and MPO signal grouping. A past county minute reported NTP, but a construction award and physical start need verification. [S01, S02, S12]
What is happening with I-55?
MDOT controls four widening/interchange priorities in the county plan. A specific Church–north of Goodman corridor received an announced $44m INFRA award September 28. [S01, S08]
What is the $44 million award?
An announced federal INFRA award for MDOT's I-55/I-69 Church–approximately one mile north of SR 302 corridor, including lane and interchange improvements; not a sum for all four county-plan phases. [S08]
When will I-55 construction begin?
MDOT lists a February 2027 proposed letting for the relevant reconstruction/widening contract. A letting is a procurement milestone, not a construction start date. [S10]
What is happening with Highway 305?
The county prioritizes widening Church–Byhalia. A separate 2026 bill proposed money for Church–I-269, while a 2025 project near the Tennessee line was pavement maintenance. [S01, S09, S17]
Is Highway 305 widening funded?
The county plan alone does not establish construction funding; introduced bill language is not an appropriation. Check a later enacted funding record before changing this answer. [S01, S09]
Who controls these projects?
The lead varies: MDOT controls state/interstate projects; DeSoto County leads some local sections; Southaven and Olive Branch have city work; the MPO programs transportation funds but is not every road's owner. [S01, S02, S03]
How much will the projects cost?
Each card distinguishes an estimated total from phase programming, a contract award and actual spending. A single combined county spending total cannot responsibly be derived from the plan's ranges. [S01, S02]
When will they be finished?
Most prospective projects have no verified contractual completion date in the reviewed records. A city's projected July 2027 trail completion and MDOT's proposed February 2027 letting are different date types, neither a widening completion promise. [S07, S10]
Primary-Source Document Library
DeSoto County BOS 2026 four-year road plan
DeSoto County (copy hosted by DeSoto County News) · 2026-02-18 · County-authored PDF hosted by DeSoto County News
Establishes: Project priority list and estimates
Does not establish: Adoption minutes, funding, award
County-authored document hosted by DeSoto County News. Do NOT present it as county-hosted.
Checked: 2026-09-29
FY2026–29 Transportation Improvement Program
Memphis MPO · Date not established · Official PDF
Establishes: Phase programming, estimates, lead agencies and limits
Does not establish: Obligations, awards or physical construction
Checked: 2026-09-29
Getwell South Widening Project
City of Southaven · 2023-02-22 · Official city account
Establishes: Historic bid, federal allocation, start and scope
Does not establish: New Getwell sections
Checked: 2026-09-29
Board of Supervisors minutes
DeSoto County · 2021-01-19 · Official minutes
Establishes: GW-03 design task approval
Does not establish: Construction funding or award
Checked: 2026-09-29
Board of Supervisors minutes
DeSoto County · 2022-04-18 · Official minutes
Establishes: State bond accounting
Does not establish: Current balance or exact current segment spending
Checked: 2026-09-29
Southaven meeting minutes
City of Southaven · Date not established · Official minutes
Establishes: Completed historic Getwell widening listed
Does not establish: Exact acceptance date
Checked: 2026-09-29
Getwell Multi-Use Trail
City of Southaven · 2026-09-15 · Official city account
Establishes: Easement and projected trail milestones
Does not establish: Widening or actual future dates
Checked: 2026-09-29
Wicker Announces $44 Million Roadway Investment
U.S. Senator Roger Wicker · 2026-09-28 · Official press release
Establishes: Announced federal award and scope
Does not establish: Obligation, contract award, all I-55 phases
Checked: 2026-09-29
SB3324 as introduced
Mississippi Legislature · Date not established · Introduced bill text
Establishes: Proposed appropriation and Church-to-I269 language
Does not establish: Enactment or funding received
Checked: 2026-09-29
Schedule of Proposed Projects
MDOT · 2026-09-29 · Official dynamic list
Establishes: Proposed February 2027 I-55 letting
Does not establish: Construction start or contract award
Dynamic list — checked September 29, 2026. Save dated snapshot when implementing because list changes.
Checked: 2026-09-29
June 19 Board of Supervisors agenda
DeSoto County · 2026-06-19 · Official agenda
Establishes: GW-04 MOA item listed
Does not establish: Executed MOA or vote
Checked: 2026-09-29
May 2025 minutes and April 2026 agenda
DeSoto County · Date not established · Official minutes/agenda
Establishes: Reported intersection NTP and anticipated start; Apr PS&E separately in register
Does not establish: Verified award or physical work
Checked: 2026-09-29
SAP-17(18)M bid
DeSoto County · 2026-09-10 · Official advertisement
Establishes: Advertisement for overlay on three roads
Does not establish: Award or exact RP-14 mapping
Checked: 2026-09-29
Getwell Goodman–Church resurfacing
City of Southaven · 2014-09-26 · Official city account
Establishes: Historic overlay, not widening
Does not establish: Acceptance date
Checked: 2026-09-29
Getwell and Robertson Gin state aid overlay bid
DeSoto County · 2023-05-18 · Official bid advertisement
Establishes: Historic overlay solicitation
Does not establish: Widening completion
Checked: 2026-09-29
PATH project list
MDOT · Date not established · Official dynamic list
Establishes: Separate pavement rehabilitation listing
Does not establish: New widening physical status
Checked: 2026-09-29
April 2025 letting
MDOT · 2025-04-30 · Official letting record
Establishes: SR305 microsurfacing scope
Does not establish: Church–Byhalia widening
Checked: 2026-09-29
April 20 Board agenda PS&E item
DeSoto County · 2026-04-20 · Official agenda
Establishes: Getwell/Pleasant Hill intersection PS&E listed
Does not establish: Contract award or physical work
Checked: 2026-09-29
Unresolved Records
These are legitimate tracker data. Do not hide uncertainty from readers. Do not fill the gaps.
U01 · UNKNOWN
County-hosted/adopted February plan confirmation
U02 · UNKNOWN
Executed June 2026 GW-04 MOA
U03 · UNKNOWN
GW-04 0.5 versus 0.95 mile discrepancy
U04 · UNKNOWN
GW-02 actual ROW acquisition status
U05 · UNKNOWN
GW-03 ROW completion
U06 · UNKNOWN
GW-04 actual ROW acquisition status
U07 · UNKNOWN
GW-02/03/04 utility relocation
U08 · UNKNOWN
GW-05 construction contract award and amount
U09 · UNKNOWN
GW-05 physical construction start
U10 · UNKNOWN
I-55 complete funding breakdown and exact award/phase overlap
U11 · UNKNOWN
I-55 letting result and construction contract
U12 · UNKNOWN
Highway 305 enacted funding and exact limits
U13 · UNKNOWN
Contractors with no verified award
U14 · UNKNOWN
Exact completion/acceptance dates
U15 · UNKNOWN
Getwell environmental determinations
U16 · UNKNOWN
RP-14 to SAP-17(18)M exact mapping
U17 · UNKNOWN
Municipal boundaries for each corridor section
U18 · UNKNOWN
January 2026 Getwell interlocal agreement outcome
Update Log
2026-09-29 — BASELINE-2026-09-29
Last checked: 2026-09-29 · Last changed: null
Initial publication baseline assembled from Phase 12 public records; unknowns preserved; no live project status asserted beyond sourced records.