DE SOTO COUNTY · ROAD PROJECTS · VERIFIED THROUGH SEPTEMBER 29, 2026

Maintained, source-backed road project tracker — not a standard article. Evidence cutoff: September 29, 2026.

DeSoto County Road Projects: Getwell Road, I-55, Highway 305 & Current Status

DeSoto County's February 2026 four-year road plan names 15 projects and a separate list of nine longer-range priorities. They include county, city and MDOT roads; appearing on the list does not mean a project has construction money or an awarded contract. Getwell Road has several distinct sections: Southaven's Church Road–Star Landing widening is completed, while other sections have different design, right-of-way and planning records. A $44 million federal INFRA award was announced September 28 for an MDOT I-55/I-69 corridor, but it does not fund every interstate phase in the county plan. Highway 305's proposed widening must also be separated from maintenance work and proposed legislation. Use the segment and phase records below to see what is established and what remains unknown. [S01, S02, S03, S06, S08, S10]

Statuses describe the cited record as of the baseline, not live traffic or a guarantee that a projected date will be met. "No award located" describes this investigation, not proof that no award exists.

Evidence Rules

  • · County priority ≠ funding
  • · Estimated cost ≠ appropriation
  • · Design/ROW programming ≠ construction funding
  • · Proposed letting ≠ contract award
  • · Award ≠ notice to proceed
  • · NTP ≠ observed physical work
  • · Nearby work ≠ the same contract
  • · Maintenance ≠ widening
  • · One Getwell section ≠ the whole corridor
  • · County plan entry ≠ county-controlled project
  • · Federal award for one corridor ≠ funding for every phase
  • · Projected completion ≠ contractual or actual completion

Current Status Dashboard

WHAT IS COMPLETED?

COMPLETED

GW-01 Church–Star Landing widening; city record reports completion. Exact acceptance date unverified.

WHAT IS IN DESIGN?

DESIGN

GW-02 and GW-04 have TIP design phases programmed; GW-03 design task historically approved. "Design complete" for Starlanding 1/4 is only a county plan label.

WHAT IS IN ROW?

ROW

GW-03 county plan says "In ROW"; GW-02/04 have FY2027 ROW programmed; GW-05 plan says ROW. No acquisition completion inferred.

WHAT HAS PROGRAMMED FUNDING?

PROGRAMMED

GW-02/GW-04 design and ROW; RP-01 ROW; GW-05 signal construction grouping. Report phase and source.

WHAT HAS A VERIFIED CONSTRUCTION AWARD?

AWARDED

GW-01 historical low bid reported; no prospective Getwell widening award established here.

WHAT IS UNDER CONSTRUCTION?

UNDER CONSTRUCTION

No prospective Getwell widening section established as physically under construction. Do not claim none anywhere countywide without checking each agency.

WHAT IS LONGER RANGE?

LONGER RANGE

Nine separately labeled county priorities; GW-02/04 also have current programmed preconstruction phases.

Getwell Road Widening: Which Section Is Which?

Pleasant Hill–Lester and Pleasant Hill–I-269 are not the same Getwell Road project. The first runs north from Pleasant Hill to Lester (GW-03); the second runs south from Pleasant Hill toward I-269 (GW-04). Star Landing–Lester (GW-02) is another northern section. Southaven's Church–Star Landing widening (GW-01) is an older completed project. The intersection at Pleasant Hill (GW-05) and Central Parkway–Church trail (GW-06) have their own scopes.

GW-01: Church Road → Star Landing Road

Project: MS-LSTP-2014-01

Lead: Southaven

COMPLETED

Two to five lanes; median, College signal; city reported $14,060,127 low bid, $7,887,061 federal allocation, March 1, 2023 actual stated construction start; later city record lists completion.

Actual start: 2023-03-01

Exact acceptance date null; don't reuse old start for GW-02/03/04. County's $875,000 assistance for Star Landing intersection is not another whole-road cost.

Sources: S03, S06

GW-02: Star Landing Road → Lester Road

Project: MS-STBG-2026-02

Lead: DeSoto County

DESIGN/ROW

TIP 0.94 mi, 2→4 divided lanes. DeSoto County lead, Southaven geography/partner.

Estimated total:
$12,792,712
Design FY2026:
$808,082 ($646,466 federal / $161,616 local)
ROW FY2027:
$559,193 ($447,355 federal / $111,838 local)

Length: 0.94 mile · Lanes: 2 → 4

Construction phase not shown in adopted TIP; no construction award/start established. Estimated total ≠ construction funding.

Sources: S01, S02

GW-03: Lester Road → Pleasant Hill Road

Lead: DeSoto County

ROW

About 0.5 mi, 2→5 lanes. Waggoner design task approved in 2021.

Estimated total:
$5.5–6.5m

Length: 0.5 mile · Lanes: 2 → 5

ROW complete null; bond balance/current eligible scope null; construction funding/award/NTP/work/contractor/completion null. Plan "in ROW" is not ROW completion.

Sources: S01, S04, S05

GW-04: Pleasant Hill Road → I-269

Project: MS-STBG-2026-01

Lead: DeSoto County

DESIGN/ROW

TIP: 0.95 mi, 2→5 lanes. DeSoto County lead, Hernando geography/partner.

TIP estimated total:
$10,752,318
County estimate:
$10–12m
Design FY2026:
$646,466 ($517,173 federal / $129,293 local)
ROW FY2027:
$559,193 ($447,355 federal / $111,838 local)

SOURCE DISCREPANCY — NOT YET RECONCILED

County plan: approximately 0.5 mile

MPO TIP: 0.95 mile

Length: 0.95 mile · Lanes: 2 → 5

County longer-range plan says about 0.5 mi: unresolved length conflict. Construction phase not shown in adopted TIP. June 2026 agenda references MOA; execution unverified.

Sources: S01, S02, S11

GW-05: Getwell Road × Pleasant Hill Road (Intersection)

Lead: DeSoto County

INTERSECTION

Separate signal and turn-lane intersection project. County plan ROW, estimate $2–3m. MPO grouping lists $3,840,845 federal construction programming.

County estimate:
$2–3m
MPO federal:
$3,840,845 federal construction programming

May 2025 minutes reported NTP received and anticipated summer 2026 MDOT start; April 2026 agenda referenced PS&E. Verify NTP instrument, what work it covers, contract award and actual physical start; do not label under construction.

Sources: S01, S02, S12

GW-06: Central Parkway → Church Road (Multi-Use Trail)

Lead: Southaven

TRAIL

Southaven multi-use trail, NOT widening. Easements acquired. Approximately $800k projected after bidding.

Bidding:
November 2026 — PROJECTED
Construction:
Spring 2027 — PROJECTED
Completion:
July 2027 — PROJECTED

Contractor/award/start/actual completion null; excluded from widening totals. Never include GW-06 in Getwell widening totals.

Sources: S07

Getwell Corridor Schematic

SCHEMATIC — NOT TO SCALE

Church
GW-01 completed
Star Landing
GW-02 design/ROW programmed
Lester
GW-03 in ROW per plan
Pleasant Hill(GW-05 separate intersection)
GW-04 design/ROW programmed
I-269

North to south. GW-06 (trail) shown separately — not a widening segment.

I-55/I-69 Widening Phases

Phase 1: Goodman → Church

ESTIMATED PROJECT COST: $156m

4 → 8 lanes (county plan)

Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.

Phase 2: Church → I-269

ESTIMATED PROJECT COST: $168m

4 → 8 lanes (county plan)

Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.

Phase 3: Starlanding interchange

ESTIMATED PROJECT COST: $45m

4 → 8 lanes (county plan)

Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.

Phase 4: Commerce interchange → Starlanding

ESTIMATED PROJECT COST: $50m

4 → 6 lanes plus interchange changes (county plan)

Lead: MDOT. Do not say these are county construction contracts. Do not say all phases are funded.

September 28, 2026 · $44 MILLION · INFRA FEDERAL AWARD ANNOUNCED

Lead: MDOT

Corridor: Church Road → approximately one mile north of SR 302/Goodman Road

Lane description: 4 → 10 lanes per Sep 28 award source

SOURCE DISCREPANCY — NOT YET RECONCILED

February county plan: 4 → 8 lanes. September award announcement: 4 → 10 lanes.

Attribute each. Do not reconcile them yourself.

This is a specific corridor award. It does NOT establish funding for all four I-55 phases. Do not automatically subtract $44m from the $156m Phase 1 estimate.

PROPOSED LETTING — SUBJECT TO CHANGE

MDOT proposed letting: February 2027

Project: NH-0055-04(077)V21 / 100222/303000

Contractor: UNKNOWN

Contract award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

Never: "Construction starts February 2027." A letting is a procurement milestone, not a construction start date.

MDOT's I-55/I-69 mill and overlay between I-269 and Church is pavement rehabilitation, not proof that the four widening phases began. [S16]

Highway 305

Three separate records. Never merge widening, legislative proposals, and maintenance.

H305-W: WIDENING

Corridor: Church → Byhalia

Lead: MDOT

Status: County priority

Funding: NOT ESTABLISHED

County plan alone does not establish construction funding.

Sources: S01

H305-BILL: LEGISLATIVE PROPOSAL

Corridor: Church → I-269

Lead: Mississippi Legislature

Bill: SB3324 introduced text

Status: PROPOSED APPROPRIATION

Funding: NOT ESTABLISHED — introduced language is not funding

Do not call funded. Enactment not established from the cited primary bill text.

Sources: S09

H305-M: MAINTENANCE

Corridor: Approximately 1.6 miles near Tennessee line

Lead: MDOT

Work: Scrub seal / microsurfacing

Letting: April 30, 2025

Status: MAINTENANCE

Never present maintenance as widening.

Sources: S17

Project Inventory

All 15 four-year and 9 longer-range source records. Use filters to narrow by corridor, agency, type, or plan list.

24 of 24 records

RP-01FOUR YEAR

Starlanding Road (Segment 3)

Starlanding Road

Cumberland Road → Swinnea Road

Lead: DeSoto County

Type: ROAD WIDENING

Plan status: ROW

Estimate: $9–12m

Verified: 2026-09-29

RP-02FOUR YEAR

Getwell/Pleasant Hill intersection

Getwell Road

Getwell Road → Pleasant Hill Road

Lead: DeSoto County

Type: INTERSECTION SIGNAL

Plan status: ROW

Estimate: $2–3m

Verified: 2026-09-29

RP-03FOUR YEAR

Getwell (Pleasant Hill to Lester)

Getwell Road

Pleasant Hill Road → Lester Road

Lead: DeSoto County

Type: ROAD WIDENING

Plan status: IN ROW

Estimate: $5.5–6.5m

Verified: 2026-09-29

RP-04FOUR YEAR

Ingrams Mill Road Bridge

Ingrams Mill Road

Lead: UNKNOWN

Type: BRIDGE REPLACEMENT

Plan status: ROW

Estimate: $2–3m

Verified: 2026-09-29

RP-05FOUR YEAR

I-55 Phase 1

I-55/I-69

Goodman Road → Church Road

Lead: MDOT

Type: INTERSTATE WIDENING

Plan status: MDOT PHASE 1

Estimate: $156m

Verified: 2026-09-29

RP-06FOUR YEAR

I-55 Phase 2

I-55/I-69

Church Road → I-269

Lead: MDOT

Type: INTERSTATE WIDENING

Plan status: MDOT PHASE 2

Estimate: $168m

Verified: 2026-09-29

RP-07FOUR YEAR

I-55 Phase 3

I-55/I-69

Starlanding interchange → Starlanding interchange

Lead: MDOT

Type: INTERCHANGE

Plan status: MDOT PHASE 3

Estimate: $45m

Verified: 2026-09-29

RP-08FOUR YEAR

I-55 Phase 4

I-55/I-69

Commerce interchange → Starlanding

Lead: MDOT

Type: INTERSTATE INTERCHANGE

Plan status: MDOT PHASE 4

Estimate: $50m

Verified: 2026-09-29

RP-09FOUR YEAR

U.S. 51

U.S. 51

Venture Drive → Green T Road

Lead: MDOT

Type: STATE HIGHWAY WIDENING

Plan status: MDOT

Estimate: Not established

Verified: 2026-09-29

RP-10FOUR YEAR

Highway 305

Highway 305

Church Road → Byhalia Road

Lead: MDOT

Type: STATE HIGHWAY WIDENING

Plan status: MDOT

Estimate: Not established

Verified: 2026-09-29

RP-11FOUR YEAR

Holly Springs–Jaybird

Holly Springs Road

Holly Springs Road → Jaybird Road

Lead: UNKNOWN

Type: ROUNDABOUT

Plan status: ROW

Estimate: $3m

Verified: 2026-09-29

RP-12FOUR YEAR

Hacks Cross Road

Hacks Cross Road

College Road → Bethel Park

Lead: UNKNOWN

Type: ROAD WIDENING

Plan status: ROW

Estimate: $7.2m

Verified: 2026-09-29

RP-13FOUR YEAR

Byhalia–Jaybird

Byhalia Road

Byhalia Road → Jaybird Road

Lead: UNKNOWN

Type: ROUNDABOUT

Plan status: PLANNING

Estimate: $4m

Verified: 2026-09-29

RP-14FOUR YEAR

Holly Springs/Nail/Nesbit overlay

Holly Springs/Nail/Nesbit

Lead: DeSoto County

Type: OVERLAY

Plan status: DESIGN

Estimate: $3.4m

Verified: 2026-09-29

RP-15FOUR YEAR

Malone Road Bridge

Malone Road

Lead: UNKNOWN

Type: BRIDGE REPLACEMENT

Plan status: DESIGN

Estimate: $925k

Verified: 2026-09-29

LR-01LONGER RANGE

Craft widening, Freedom–I-269

Craft Road

Freedom Road → I-269

Lead: UNKNOWN

Type: ROAD WIDENING

Plan status: 5–15 YEAR PRIORITY

Estimate: null

Verified: 2026-09-29

LR-02LONGER RANGE

Pleasant Hill/McIngvale

Pleasant Hill Road

Pleasant Hill Road → McIngvale Road

Lead: UNKNOWN

Type: INTERSECTION SIGNAL OR ROUNDABOUT

Plan status: 5–15 YEAR PRIORITY

Estimate: TBD

Verified: 2026-09-29

LR-03LONGER RANGE

Laughter/Byhalia

Laughter/Byhalia

Laughter Road → Byhalia Road

Lead: UNKNOWN

Type: INTERSECTION CULVERT

Plan status: 5–15 YEAR PRIORITY

Estimate: TBD

Verified: 2026-09-29

LR-04LONGER RANGE

Byhalia–Jaybird (longer range)

Byhalia Road

Byhalia Road → Jaybird Road

Lead: UNKNOWN

Type: ROUNDABOUT

Plan status: 5–15 YEAR PRIORITY

Estimate: $4m

Verified: 2026-09-29

LR-05LONGER RANGE

Craft alignment, College–Bethel

Craft Road

College Road → Bethel Road

Lead: UNKNOWN

Type: NEW ROAD

Plan status: 5–15 YEAR PRIORITY

Estimate: TBD

Verified: 2026-09-29

LR-06LONGER RANGE

Starlanding Segment 4

Starlanding Road

Baptist Road → Getwell Road

Lead: DeSoto County

Type: ROAD RECONSTRUCTION

Plan status: 5–15 YEAR PRIORITY

Estimate: $10–14m

Verified: 2026-09-29

LR-07LONGER RANGE

Starlanding Segment 1

Starlanding Road

Tulane Road → Railroad

Lead: DeSoto County

Type: ROAD RECONSTRUCTION

Plan status: 5–15 YEAR PRIORITY

Estimate: TBD

Verified: 2026-09-29

LR-08LONGER RANGE

Getwell Pleasant Hill–I-269 (longer range)

Getwell Road

Pleasant Hill Road → I-269

Lead: DeSoto County

Type: ROAD WIDENING

Plan status: 5–15 YEAR PRIORITY

Estimate: $10–12m

Verified: 2026-09-29

LR-09LONGER RANGE

Getwell Star Landing–Lester (longer range)

Getwell Road

Star Landing Road → Lester Road

Lead: DeSoto County

Type: ROAD WIDENING

Plan status: 5–15 YEAR PRIORITY

Estimate: $12–14m

Verified: 2026-09-29

Funding, Cost, ROW and Procurement

NON-ADDITIVE LEDGER

These numbers represent different categories and stages and cannot responsibly be combined into one total-spending figure. Never calculate a site-wide "DeSoto County is spending $X million on roads."

Each project shows four distinct fields: ESTIMATED TOTAL PROJECT COST, PROGRAMMED PHASE FUNDING, CONSTRUCTION CONTRACT AWARD, and SPENT TO DATE. Missing amounts read "Not established in reviewed records," not "$0."

Funding Records

F01ESTIMATED COST

$12,792,712

Project: GW-02 · Phase: whole project

Source: MPO TIP

Not construction funding

F02PROGRAMMED

$808,082

Project: GW-02 · Phase: design FY2026

Source: MPO STBG-M-MS/local

Not obligated/spent; federal $646,466, local $161,616

F03PROGRAMMED

$559,193

Project: GW-02 · Phase: ROW FY2027

Source: MPO STBG-M-MS/local

Not acquired; federal $447,355, local $111,838

F04ESTIMATED COST

$10,752,318

Project: GW-04 · Phase: whole project

Source: MPO TIP

Not construction funding

F05PROGRAMMED

$646,466

Project: GW-04 · Phase: design FY2026

Source: MPO STBG-M-MS/local

Federal $517,173, local $129,293

F06PROGRAMMED

$559,193

Project: GW-04 · Phase: ROW FY2027

Source: MPO STBG-M-MS/local

Federal $447,355, local $111,838

F07ESTIMATED COST

$5.5–6.5m

Project: GW-03 · Phase: whole project

Source: County plan

Range; not appropriated

F08STATE AWARD

$1.5m

Project: GW-03 · Phase: historical bond account

Source: Mississippi state bond

Current balance, exact segment allocation, obligations and spent amount unknown

F09PROGRAMMED

$3,840,845

Project: GW-05 · Phase: signal construction grouping

Source: MPO STBG federal

Not the final contract amount

F10ESTIMATED COST

$156m

Project: RP-05 · Phase: plan phase 1 total

Source: County plan

Not construction award or full funding

F11FEDERAL AWARD

$44m

Project: I55-AWARD-01 · Phase: Church to north of SR302 corridor

Source: INFRA

Announced award; not every phase, obligated/spent/contract amount unknown

F12CONTRACT AWARD

$14,060,127

Project: GW-01 · Phase: historical widening low bid

Source: Southaven report

Reported lowest bid; not later prospective sections

F13PROGRAMMED

$7,887,061

Project: GW-01 · Phase: historical federal allocation

Source: Federal via MPO/MDOT

Reported allocation; not spending proof

F14PROGRAMMED

$2,000,001

Project: RP-01 · Phase: ROW

Source: Federal earmark/local

Federal $1,600,001 and local $400,000; not whole project cost

F15ESTIMATED COST

~$800k

Project: GW-06 · Phase: trail whole project

Source: Southaven

Approximate city projection, not bid amount

ROW / Utility Status

GW-02

ROW: ROW PROGRAMMED

Utility: UNKNOWN

Sources: S02

GW-03

ROW: ROW ACTIVE PER COUNTY PLAN

Utility: UNKNOWN

Sources: S01

GW-04

ROW: ROW PROGRAMMED

Utility: UNKNOWN

Sources: S02

GW-05

ROW: ROW PER COUNTY PLAN

Utility: UNKNOWN

Sources: S01

GW-06

ROW: EASEMENTS ACQUIRED

Utility: UNKNOWN

Sources: S07

RP-01

ROW: ROW PROGRAMMED

Utility: UNKNOWN

Sources: S01, S02

Procurement / Construction Status

GW-02

Bid stage: NOT LOCATED

Award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

GW-03

Bid stage: NOT LOCATED

Award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

GW-04

Bid stage: NOT LOCATED

Award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

GW-05

Bid stage: NOT LOCATED

Award: NOT VERIFIED

NTP: REPORTED IN 2025 MINUTES

Physical construction: NOT VERIFIED

GW-06

Bid stage: PROJECTED NOV 2026

Award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

RP-05

Bid stage: PROPOSED FEB 2027

Award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

RP-14

Bid stage: POSSIBLE MATCH ADVERTISED

Award: NOT LOCATED

NTP: NOT LOCATED

Physical construction: NOT VERIFIED

Who Is Responsible for DeSoto County Road Projects?

A road being located in DeSoto County does not mean DeSoto County controls the project.

DeSoto County

County plans/priorities and lead on TIP GW-02, GW-04 and Starlanding Segment 3; county Getwell GW-03 and intersection GW-05. Partners may share costs.

MDOT

Lead for interstate, U.S. 51 and state Highway 305 entries; publishes state schedules and lettings.

Southaven

Lead for completed GW-01 and separate GW-06 trail; partner/geography on GW-02.

Olive Branch

Associated with Hacks Cross county collaboration and leads other distinct MPO projects, including Pleasant Hill Road widening.

Hernando

Geography/partner reflected in MPO for GW-04; MPO lists DeSoto County as lead.

Horn Lake

Municipality with its own roads and MPO projects; no sole-lead entry in the 15-row county list established.

Memphis MPO

Programs eligible transportation phases and federal allocations; does not thereby become the road owner or construction contractor.

Federal programs

INFRA award and TIP funds apply to specified projects/phases, not every project in the county.

Project Timeline

Solid markers = documented past events. Outlined markers = planned/projected events. Do not change planned milestones to completed merely because their projected date passes.

RECORD DATE

2021-01-19

County approved design task for Lester–Pleasant Hill

Source: S04

RECORD DATE

2022-04-18

County recorded $1.5m state bond accounting for Getwell/Pleasant Hill

Source: S05

ACTUAL START

2023-03-01

Southaven stated start of Church–Star Landing widening

Source: S03

ACTUAL COMPLETION

Date not established

Later Southaven meeting record lists project completion; exact date not established

Source: S06

RECORD DATE

2025-05-22

County minutes reported NTP received and anticipated summer 2026 MDOT start; physical start unverified

Source: S12

RECORD DATE

2026-02-18

County four-year and longer-range plan dated

Source: S01

PROGRAM YEAR

2026

Adopted TIP programs design in FY2026, ROW in FY2027; no construction phase shown

Source: S02

RECORD DATE

2026-06-19

County agenda references I-269–Pleasant Hill MOA approval item; execution unverified

Source: S11

RECORD DATE

2026-09-15

Southaven reports easements acquired and projected bid/start/completion

Source: S07

RECORD DATE

2026-09-28

$44m INFRA award announced for specified MDOT corridor

Source: S08

PROPOSED LETTING

2027-02

MDOT proposed reconstruction/widening letting; subject to change

Source: S10

BID DATE

2026-11

Southaven projected trail bidding, not advertisement

Source: S07

PROJECTED COMPLETION

2027-07

Southaven projected trail completion, not contractual date

Source: S07

Frequently Asked Questions

What road projects are planned in DeSoto County?

The county's February 2026 plan lists 15 four-year entries and nine separate longer-range priorities. They range from Getwell and Starlanding to MDOT highways and bridge, intersection and overlay work. A plan entry alone does not confirm funding or construction. [S01]

What roads are currently being widened?

The reviewed records establish a completed Getwell widening and future/programmed sections, plus an MDOT interstate widening proposal and federal award. They do not establish that the prospective Getwell sections are physically under construction. This tracker is not a live roadwork feed. [S02, S06, S08]

What is happening with Getwell Road?

Several separate sections have different agencies and stages. Church–Star Landing is completed; Star Landing–Lester and Pleasant Hill–I-269 have programmed design/ROW; the county plan says Lester–Pleasant Hill is in ROW. [S01, S02, S06]

How many Getwell projects are tracked?

Six records: four consecutive widening sections, a separate Pleasant Hill intersection, and a separate trail. Only the first four are widening sections. [S01, S02, S03, S07]

Is Getwell Road being widened now?

No prospective widening section's physical construction start is established by the reviewed records. The completed Church–Star Landing work is often present in older results. [S03, S06]

What is happening between Star Landing and Lester?

MPO MS-STBG-2026-02 programs design in FY2026 and ROW in FY2027 for about 0.94 mile; it does not show construction programming in the adopted TIP. [S02]

What is happening between Lester and Pleasant Hill?

The county's four-year plan labels approximately 0.5 mile "In ROW." A design task and historical state bond activity are documented, but ROW completion and construction award are unverified. [S01, S04, S05]

What is happening between Pleasant Hill and I-269?

MPO MS-STBG-2026-01 programs design and ROW, not construction; its 0.95-mile length differs from the county list's approximately 0.5 mile. [S01, S02]

Are Pleasant Hill–Lester and Pleasant Hill–I-269 the same project?

No. They meet at Pleasant Hill but extend in opposite directions and have different records. [S01, S02]

When will Getwell construction start?

There is no verified construction start date for GW-02, GW-03 or GW-04. The March 2023 start belonged to the now completed Southaven section. [S02, S03]

Is Getwell widening fully funded?

The TIP programs design/ROW for GW-02 and GW-04; their estimated total costs are not construction appropriations. Full construction funding is not established in these records. [S02]

What is happening at Getwell and Pleasant Hill?

A separate county signal and turn-lane project appears in the plan and MPO signal grouping. A past county minute reported NTP, but a construction award and physical start need verification. [S01, S02, S12]

What is happening with I-55?

MDOT controls four widening/interchange priorities in the county plan. A specific Church–north of Goodman corridor received an announced $44m INFRA award September 28. [S01, S08]

What is the $44 million award?

An announced federal INFRA award for MDOT's I-55/I-69 Church–approximately one mile north of SR 302 corridor, including lane and interchange improvements; not a sum for all four county-plan phases. [S08]

When will I-55 construction begin?

MDOT lists a February 2027 proposed letting for the relevant reconstruction/widening contract. A letting is a procurement milestone, not a construction start date. [S10]

What is happening with Highway 305?

The county prioritizes widening Church–Byhalia. A separate 2026 bill proposed money for Church–I-269, while a 2025 project near the Tennessee line was pavement maintenance. [S01, S09, S17]

Is Highway 305 widening funded?

The county plan alone does not establish construction funding; introduced bill language is not an appropriation. Check a later enacted funding record before changing this answer. [S01, S09]

Who controls these projects?

The lead varies: MDOT controls state/interstate projects; DeSoto County leads some local sections; Southaven and Olive Branch have city work; the MPO programs transportation funds but is not every road's owner. [S01, S02, S03]

How much will the projects cost?

Each card distinguishes an estimated total from phase programming, a contract award and actual spending. A single combined county spending total cannot responsibly be derived from the plan's ranges. [S01, S02]

When will they be finished?

Most prospective projects have no verified contractual completion date in the reviewed records. A city's projected July 2027 trail completion and MDOT's proposed February 2027 letting are different date types, neither a widening completion promise. [S07, S10]

Primary-Source Document Library

S01

DeSoto County BOS 2026 four-year road plan

DeSoto County (copy hosted by DeSoto County News) · 2026-02-18 · County-authored PDF hosted by DeSoto County News

Establishes: Project priority list and estimates

Does not establish: Adoption minutes, funding, award

County-authored document hosted by DeSoto County News. Do NOT present it as county-hosted.

Checked: 2026-09-29

Source link

S02

FY2026–29 Transportation Improvement Program

Memphis MPO · Date not established · Official PDF

Establishes: Phase programming, estimates, lead agencies and limits

Does not establish: Obligations, awards or physical construction

Checked: 2026-09-29

Source link

S03

Getwell South Widening Project

City of Southaven · 2023-02-22 · Official city account

Establishes: Historic bid, federal allocation, start and scope

Does not establish: New Getwell sections

Checked: 2026-09-29

Source link

S04

Board of Supervisors minutes

DeSoto County · 2021-01-19 · Official minutes

Establishes: GW-03 design task approval

Does not establish: Construction funding or award

Checked: 2026-09-29

Source link

S05

Board of Supervisors minutes

DeSoto County · 2022-04-18 · Official minutes

Establishes: State bond accounting

Does not establish: Current balance or exact current segment spending

Checked: 2026-09-29

Source link

S06

Southaven meeting minutes

City of Southaven · Date not established · Official minutes

Establishes: Completed historic Getwell widening listed

Does not establish: Exact acceptance date

Checked: 2026-09-29

Source link

S07

Getwell Multi-Use Trail

City of Southaven · 2026-09-15 · Official city account

Establishes: Easement and projected trail milestones

Does not establish: Widening or actual future dates

Checked: 2026-09-29

Source link

S08

Wicker Announces $44 Million Roadway Investment

U.S. Senator Roger Wicker · 2026-09-28 · Official press release

Establishes: Announced federal award and scope

Does not establish: Obligation, contract award, all I-55 phases

Checked: 2026-09-29

Source link

S09

SB3324 as introduced

Mississippi Legislature · Date not established · Introduced bill text

Establishes: Proposed appropriation and Church-to-I269 language

Does not establish: Enactment or funding received

Checked: 2026-09-29

Source link

S10

Schedule of Proposed Projects

MDOT · 2026-09-29 · Official dynamic list

Establishes: Proposed February 2027 I-55 letting

Does not establish: Construction start or contract award

Dynamic list — checked September 29, 2026. Save dated snapshot when implementing because list changes.

Checked: 2026-09-29

Source link

S11

June 19 Board of Supervisors agenda

DeSoto County · 2026-06-19 · Official agenda

Establishes: GW-04 MOA item listed

Does not establish: Executed MOA or vote

Checked: 2026-09-29

Source link

S12

May 2025 minutes and April 2026 agenda

DeSoto County · Date not established · Official minutes/agenda

Establishes: Reported intersection NTP and anticipated start; Apr PS&E separately in register

Does not establish: Verified award or physical work

Checked: 2026-09-29

Source link

S13

SAP-17(18)M bid

DeSoto County · 2026-09-10 · Official advertisement

Establishes: Advertisement for overlay on three roads

Does not establish: Award or exact RP-14 mapping

Checked: 2026-09-29

Source link

S14

Getwell Goodman–Church resurfacing

City of Southaven · 2014-09-26 · Official city account

Establishes: Historic overlay, not widening

Does not establish: Acceptance date

Checked: 2026-09-29

Source link

S15

Getwell and Robertson Gin state aid overlay bid

DeSoto County · 2023-05-18 · Official bid advertisement

Establishes: Historic overlay solicitation

Does not establish: Widening completion

Checked: 2026-09-29

Source link

S16

PATH project list

MDOT · Date not established · Official dynamic list

Establishes: Separate pavement rehabilitation listing

Does not establish: New widening physical status

Checked: 2026-09-29

Source link

S17

April 2025 letting

MDOT · 2025-04-30 · Official letting record

Establishes: SR305 microsurfacing scope

Does not establish: Church–Byhalia widening

Checked: 2026-09-29

Source link

S12B

April 20 Board agenda PS&E item

DeSoto County · 2026-04-20 · Official agenda

Establishes: Getwell/Pleasant Hill intersection PS&E listed

Does not establish: Contract award or physical work

Checked: 2026-09-29

Source link

Unresolved Records

These are legitimate tracker data. Do not hide uncertainty from readers. Do not fill the gaps.

U01 · UNKNOWN

County-hosted/adopted February plan confirmation

U02 · UNKNOWN

Executed June 2026 GW-04 MOA

U03 · UNKNOWN

GW-04 0.5 versus 0.95 mile discrepancy

U04 · UNKNOWN

GW-02 actual ROW acquisition status

U05 · UNKNOWN

GW-03 ROW completion

U06 · UNKNOWN

GW-04 actual ROW acquisition status

U07 · UNKNOWN

GW-02/03/04 utility relocation

U08 · UNKNOWN

GW-05 construction contract award and amount

U09 · UNKNOWN

GW-05 physical construction start

U10 · UNKNOWN

I-55 complete funding breakdown and exact award/phase overlap

U11 · UNKNOWN

I-55 letting result and construction contract

U12 · UNKNOWN

Highway 305 enacted funding and exact limits

U13 · UNKNOWN

Contractors with no verified award

U14 · UNKNOWN

Exact completion/acceptance dates

U15 · UNKNOWN

Getwell environmental determinations

U16 · UNKNOWN

RP-14 to SAP-17(18)M exact mapping

U17 · UNKNOWN

Municipal boundaries for each corridor section

U18 · UNKNOWN

January 2026 Getwell interlocal agreement outcome

Update Log

2026-09-29 — BASELINE-2026-09-29

Last checked: 2026-09-29 · Last changed: null

Initial publication baseline assembled from Phase 12 public records; unknowns preserved; no live project status asserted beyond sourced records.

Related DeSoto County Coverage