PROJECT TRACKER · VERIFIED THROUGH SEPTEMBER 28, 2026

Maintained, source-backed project tracker — not a standard article. Evidence cutoff: September 28, 2026.

Dauphin Island West End Restoration: Project Status, Funding and Construction Timeline

The Dauphin Island West End beach and dune restoration has approved implementation funding and, according to the Town, its required permits. Private easements are still being gathered. Final design and bidding are scheduled for fall 2026; construction is planned for winter 2027. As of September 28, 2026, our review found no publicly posted West End construction solicitation, contract award, notice to proceed or evidence of physical construction. An absence from the reviewed public records does not establish that no unpublished activity exists.

Funding approved ≠ funds spent·Permit issued ≠ work begun·Planned date ≠ confirmed start

FUNDED / PERMITTED / DESIGN AND EASEMENTS IN PROGRESS; CONSTRUCTION NOT VERIFIED

Has Construction Started?

No public evidence of West End physical construction was located by September 28, 2026. The Town schedules bidding for fall 2026 and construction commencement for winter 2027. Those are plans, not proof of a solicitation, contractor mobilization, or a guaranteed start date. We will update this answer when a dated bid, award, NTP or construction record appears.

This answer will be updated when:

  • •bid solicitation is posted
  • •contractor is selected
  • •contract is awarded
  • •contract is executed
  • •notice to proceed is issued
  • •mobilization occurs
  • •physical work begins

Do not automatically update the construction status merely because winter 2027 arrives.

Planned vs. Documented Milestones

30% design

Documented result: Completed

Next proof: N/A

Further design

Documented result: Documented progress toward 60% in summer 2025

Next proof: Accepted design milestone

Final design

Documented result: Planned / completion unverified

Next proof: Approved final drawing set

Major implementation funding

Documented result: $38m approved June 2026

Next proof: Obligation/disbursement record

USACE permit

Documented result: Approved December 8, 2025 per Council

Next proof: Issued instrument/conditions for register

ADEM and Beach Act permits

Documented result: Town reports issued

Next proof: Issued instruments/dates

Private easements

Documented result: Collection in progress

Next proof: Dated signed/recorded status

Construction bid

Documented result: Planned for fall; notice not located

Next proof: Posted West End IFB

Contractor, award, NTP

Documented result: Unknown / not located

Next proof: Separate dated selection, contract, NTP

Physical work

Documented result: Not established

Next proof: Documented mobilization/work

Completion

Documented result: Unknown

Next proof: Contract schedule and closeout

Project Status Tracker

NOT LOCATED means the evidence was not found in reviewed public records. It does not mean the event has been proven not to exist.

Funding

APPROVED

Evidence: RESTORE Council FPL vote, 2026-06-10; Council finding, June 2026; Town project page, checked 2026-09-28

Evidence date: 2026-06-10

Verification date: 2026-09-28

$38m implementation funding approved. Town reports full construction funding secured. Obligation and spending unverified.

What changes this status: Signed award/obligation record and disbursement reports.

Source

Permits

REPORTED ISSUED

Evidence: Council finding identifies USACE approval 2025-12-08; Town page checked 2026-09-28 reports USACE, ADEM and Beach Act permits

Evidence date: 2025-12-08

Verification date: 2026-09-28

USACE approval independently dated by Council; state issuance dates, numbers and operative conditions not verified in this packet.

What changes this status: Actual issued state instruments and complete issued USACE permit.

Source

Private easements

IN PROGRESS

Evidence: Town's Aug. 24 map and schedule

Evidence date: 2026-08-24

Verification date: 2026-09-28

Town reports POA easement recorded; continues collecting individual easements May–December 2026. No count established.

What changes this status: New dated Town count/map and recorded-instrument evidence.

Source

Final design

PLANNED

Evidence: Town page, checked 2026-09-28

Verification date: 2026-09-28

Fall 2026 completion target; no final approved construction drawings established.

What changes this status: Dated 100% design acceptance/final drawing set.

Source

Bidding

NOT LOCATED

Evidence: Town bid notices and Town page, checked 2026-09-28

Verification date: 2026-09-28

Bidding scheduled fall 2026; no West End construction solicitation found in reviewed notices.

What changes this status: West End IFB/RFP with issue date and scope.

Source

Contractor

UNKNOWN

Evidence: Town project and bid pages, checked 2026-09-28

Verification date: 2026-09-28

No selected construction firm verified. Design consultants are not the construction contractor.

What changes this status: Official selection and executed agreement.

Source

Construction contract

UNKNOWN

Evidence: Town project and bid pages, checked 2026-09-28

Verification date: 2026-09-28

No award or execution record found.

What changes this status: Council award and signed contract.

Source

Notice to proceed

NOT LOCATED

Evidence: Reviewed public project/procurement records, checked 2026-09-28

Verification date: 2026-09-28

No NTP located.

What changes this status: Dated NTP.

Source

Physical construction

NOT LOCATED

Evidence: Town's future schedule and reviewed records, checked 2026-09-28

Verification date: 2026-09-28

No evidence of West End physical work located. Winter 2027 is a target.

What changes this status: Dated mobilization/field notice, documented on-site work or construction report.

Source

Completion

UNKNOWN

Evidence: Town page, checked 2026-09-28

Verification date: 2026-09-28

No completion date confirmed. Five-year RESTORE project duration is not the sand-placement period.

What changes this status: Contract schedule, substantial-completion certificate.

Source

What Is Being Built?

Funded 2026 RESTORE description — project targets, not surveyed as-built measurements.

Linear dune

approximately 3.5 miles

Beach-compatible sand

approximately 2.4 million cubic yards

Total area

approximately 200 acres

Sandy water bottoms

approximately 40 acres

Beach/dune habitat

approximately 160 acres

How the project design descriptions changed

The older Town presentation anticipated native dune vegetation, a varying 170–590-foot initial beach width and approximately 40 acres of dune plus 200 acres of beach. Those older preliminary figures are not the current funded 40+160-acre breakdown. The USACE public notice describes borrow areas on the Mobile Pass ebb tidal shoal near Sand Island Lighthouse and a dredged-material pipeline corridor. The Town says the eventual dune location, walkovers and access points depend on final design/easements.

Source

Funding Tracker

The Town says full construction funding is secured. The Council approved $38m for implementation; earlier $993k and $1.25m support design/permitting; a separate $5m appropriation concerns dredged material. The reviewed public records do not show an authoritative current total expected cost, reconcile the older $50m–$60m estimate with the funded scope, or reveal obligation/drawdown/spending. The proposal's $30m for East End and Graveline Bay is another project, excluded from this ledger.

Do NOT calculate a $43 million project by adding $38 million and $5 million. Do NOT represent funding approval as funds spent.

NFWF Gulf Environmental Benefit Fund

Initial land-side / 30% design

Amount:
$993,000
Announced:
Early planning support
Approved/received:
RESTORE proposal calls funding received; amount cited in proposal
Obligated:
Unknown
Spent:
Unknown

Separate preparatory funding, not $38m implementation line.

Source

GOMESA

Further design and permitting

Amount:
$1,250,000
Announced:
Committed in 2024 according to proposal narrative
Approved/received:
Proposal lists received for 30%–100% design/permitting
Obligated:
Unknown
Spent:
Unknown

Design assignment does not prove final design completion.

Source

RESTORE Council 2026 FPL

Implementation / construction, inspection and monitoring

Amount:
$38,000,000
Announced:
Requested in proposal/draft FPL, late 2025
Approved/received:
Approved 2026-06-10, confirmed by Council finding
Obligated:
Unknown
Spent:
Unknown

Proposal budget estimates 97% implementation, 1% CEI, 2% monitoring; estimates are not expenditures.

Source

FY2026 federal appropriations

Beneficial use of Mobile Ship Channel material for West End

Amount:
$5,000,000
Announced:
Sen. Britt FY26 request
Approved/received:
Senator's 2026-01-21 announcement says secured in enacted funding bills
Obligated:
Project-level obligation unknown
Spent:
Unknown

Relationship to $38m implementation scope and timing unknown. Never calculate $43m project.

Source

Historical overall construction estimate

All-source cost reference

Amount:
Approximately $50m–$60m
Announced:
Reported in March 2025 coverage
Approved/received:
Not an award
Obligated:
N/A
Spent:
N/A

Historical, secondary-source estimate. No updated official all-source cost reconciliation established.

Source

Permit Register

Application submitted, public comment, approved/issued, conditions reviewed, and construction authorized to commence are independent fields — not a single progress bar.

USACE

SAM-2024-00553-DJL

Application/notice:
Town says application January 2025; USACE public notice 2025-02-05, comment deadline March 7
Issued/approved:
2025-12-08, as stated in RESTORE environmental finding
Conditions verified:
No

Scope and limitation: Federal dredging and placement/discharge authorization for West End beach/dune proposal. Public notice and permit sketches are not final contractor instructions.

Source

ADEM

State authorization

Application/notice:
Town joint application library; Town says January 2025 filing
Issued/approved:
Town reports issued; instrument number and date not verified
Conditions verified:
No

Scope and limitation: Do not infer issuance details from application index.

Source

ADCNR / Alabama Beach Project Act

Beach project / designated mean-high-tide-line

Application/notice:
Town Beach Act application library; March 6, 2025 meeting notice
Issued/approved:
Town reports issued; instrument number and date not verified
Conditions verified:
No

Scope and limitation: Beach project and designated mean-high-tide-line process. Do not determine any individual boundary/title from overview map.

Source

RESTORE Council

Environmental finding (FONSI)

Application/notice:
2026 FPL comment period 2025-11-20 to 2026-01-02
Issued/approved:
Signed FONSI, June 2026
Conditions verified:
Incorporates USACE assessment and requires adherence to applicable conditions; individual permit conditions not reproduced here

Scope and limitation: Environmental review for funding approval, not construction NTP.

Source

Property Easements

Why easements are requested

The Town seeks construction and monitoring rights on affected private land to place sand, shape and vegetate improvements, survey and maintain them. The described area is property-specific and generally runs from a parcel's southern boundary toward about the +5-foot contour or an existing structure. A project schematic is illustrative, not a parcel survey.

Duration and ownership

The older process letter describes rights to build, monitor and maintain in perpetuity; call this an ongoing construction-and-monitoring easement, not a temporary access form. The Town's FAQ says an owner continues to own the private property subject to the granted rights. Neither statement adjudicates where a particular parcel's boundary lies.

If an owner does not sign

The Town currently says it will place no sand on that property, proceed seaward of its property line, and that a low area may remain. Avoid claiming that no sand can be placed offshore/in front of it, or that an individual lot will flood.

Trackable facts

Town reports POA construction easement recorded (recording instrument/date not independently checked). Its posted easements received map is dated 2026-08-24, captioned Due October 1st. The Town separately describes individual collection May–December 2026. Show October 1 as a communicated return date and December as broader process window; do not silently make one replace the other. No reliable current count.

Requested: Unknown
Received: Unknown
Executed: Unknown
Recorded: Unknown

POA easement: reported recorded (instrument not verified) · Map snapshot: 2026-08-24 · October 1 return date · May–December 2026 collection period

Status definitions

  • requested = Town sought a grant
  • received = Town says it received paperwork
  • executed = Signed by necessary parties (only if evidenced)
  • recorded = Accepted into probate land records (only with instrument evidence or attributed Town claim)

These statuses do not automatically imply one another. No address eligibility or participation checker. No parcel-level deed database.

Procurement Watch

Planned bid seasonFall 2026
Solicitation postedNot verified in reviewed public records
Bids receivedNot verified in reviewed public records
Award approvedNot verified in reviewed public records
Contract executedNot verified in reviewed public records
Notice to proceedNot verified in reviewed public records
MobilizedNot verified in reviewed public records
CompletionNot verified in reviewed public records

Key distinctions:

  • •A bidder is not an awardee.
  • •An approved award is not an executed contract.
  • •An executed contract is not an NTP.
  • •An NTP is not proof that dredging has begun.

The Mobile County Dauphin Island Causeway Shoreline Restoration Phase 3 solicitation is a different project and must never trigger this tracker.

Project Timeline

Solid markers = documented past events. Outlined markers = planned future events. Do not change planned milestones to completed merely because their projected date passes.

STUDY · DOCUMENTED

2020

USACE/USGS barrier-island assessment identified West End as priority

Scientific antecedent, not a permit.

Source

PLANNING · REPORTED

Winter 2022

NFWF preliminary engineering support

Start of initial design phase.

Source

DESIGN · REPORTED

Spring 2023

Field investigations and modeling underway

Inputs to alternatives.

Source

DESIGN · REPORTED

Summer 2024

30% design completed

Preliminary design, not final.

Source

PLANNING · DOCUMENTED

2024-10-16

Public project presentation

Preliminary footprint and alternatives.

Source

APPLICATION · DOCUMENTED

2024-12-11

Town Beach Act/designated line hearing

Hearing step, not proof of final recording.

Source

APPLICATION · REPORTED

January 2025

USACE/ADEM and Beach Act applications

Applied, not issued.

Source

APPLICATION · DOCUMENTED

2025-02-05

USACE SAM-2024-00553-DJL public notice

Federal comment process; deadline March 7.

Source

APPLICATION · DOCUMENTED

2025-03-06

ADCNR/ADEM public meeting

State review, not issuance.

Source

DESIGN · REPORTED

Summer 2025

Progress toward 60%; dune alignment discussed

Later designs can differ from 30% sheets.

Source

FUNDING · DOCUMENTED

2025-11-20 to 2026-01-02

RESTORE draft FPL comment window

$38m then proposed.

Source

PERMIT · DOCUMENTED

2025-12-08

USACE permit approval date identified by Council

Permit milestone; conditions still to inspect.

Source

FUNDING · DOCUMENTED

2026-01-21

$5m FY26 West End dredged-material funding announced as secured

Separate federal funding line.

Source

FUNDING · DOCUMENTED

2026-06-10

RESTORE Council approves $38m

Proposal becomes approved implementation funding.

Source

PERMIT · DOCUMENTED

June 2026

RESTORE Council environmental finding signed

Funding-associated environmental review; not NTP.

Source

EASEMENT · REPORTED

May–December 2026

Town gathering individual easements

Do not treat every parcel as received.

Source

EASEMENT · DOCUMENTED

2026-08-24

Town's map of easements received

Dated snapshot, not recording ledger.

Source

EASEMENT · PLANNED

2026-10-01

Map caption's return date

Separate from Town's December collection window.

Source

DESIGN · PLANNED

Fall 2026

Final design and bidding targets

Do not mark as achieved without documents.

Source

CONSTRUCTION · PLANNED

Winter 2027

Town's target to commence construction

No fixed start or finish date.

Source

Frequently Asked Questions

Has construction started?

No public evidence of West End physical construction was located by September 28, 2026. The Town schedules bidding for fall 2026 and construction commencement for winter 2027. Those are plans, not proof of a solicitation, contractor mobilization, or a guaranteed start date.

When will construction start?

Town targets winter 2027 for construction commencement; it is a plan, not a scheduled NTP. No verified start date.

Is the project fully funded?

The Town says full construction funding is secured. The RESTORE Council approved $38m for implementation in June 2026. Earlier $993k and $1.25m support design/permitting. A separate $5m appropriation concerns dredged material. Obligation and spending are unverified.

Who is the contractor?

No selected construction firm has been verified. Design consultants are not the construction contractor. No award or execution record has been found.

What if I do not sign an easement?

The Town says it will not put sand on your property and will proceed seaward of the property line; a low area could remain. Individual effects require the final plans and a property survey.

Is the easement permanent?

Older Town materials describe continuing construction, monitoring and maintenance rights in perpetuity; the exact recorded text controls for any given property.

Will sand go in front of my property?

The Town's statement concerns placement on an unsigned private parcel. It does not provide a parcel-specific answer about offshore sand placement or final dune geometry.

Will I need a walkover?

The Town says one may be necessary where a completed dune affects access; placement depends on final design, easements, ordinances and permits. No address determination is available here.

Will beach access change?

The Town says its project will preserve existing access patterns; the proposal discusses raising side-road dune crossings. Exact construction-phase access plans and finished crossings are unverified.

Will parts of the beach close?

No final contractor closure schedule was located. Do not expect unrestricted access during construction.

Where will the sand come from?

Proposed borrow areas lie on the offshore Mobile Pass shoal near Sand Island Lighthouse; a pipeline corridor is shown in permit materials. Final operations must follow the issued permits and contractor plan.

Will the project prevent flooding?

It aims to reduce erosion and strengthen the beach/dune system; no reviewed engineering record guarantees flood prevention or protection of a particular home.

When will construction finish?

No verified completion date. The five-year RESTORE project duration is not the sand-placement period.

What does the map show?

The Town's August 24, 2026 easement map is a dated snapshot of easements received, not a recording ledger or deed database. It does not determine parcel-level participation.

What is the difference between an approved permit and construction approval?

An approved permit authorizes the proposed work under conditions; it is not a notice to proceed or evidence that construction has begun. Construction requires a separate contract, NTP and mobilization.

Primary-Source Document Library

West End project page and four-sheet easement map

Town; page checked 2026-09-28, map 2026-08-24

Establishes: Town's funding/permit claims, easement policy, future schedule, dated snapshot

Does not establish: State permit numbers/conditions, final construction award, signed deed count

Source link

2026 FPL decision / environmental finding

RESTORE Council; vote 2026-06-10, finding June

Establishes: $38m approved, USACE permit approval date, environmental finding

Does not establish: Fund disbursement, contractor NTP

Source link

West End implementation proposal

Alabama/ADCNR to RESTORE Council; proposed before June approval

Establishes: $38m request, 2.4m cubic yards, habitat targets, preliminary budget shares, separate planning support

Does not establish: Actual spending, final design, issuance of permits (it says pending at proposal time)

Source link

Alabama approval announcement

ADCNR; 2026-06-11

Establishes: June 10 vote and 40+160-acre current description

Does not establish: Contract or mobilization

Source link

USACE public notice SAM-2024-00553-DJL

USACE; 2025-02-05

Establishes: Application scope, offshore borrow areas, review process

Does not establish: Issued permit or final conditions

Source link

Joint USACE/ADEM application index and technical attachments

Town; Jan 2025 application era

Establishes: Preliminary design, sketches, draft easement, borrow study and monitoring plan

Does not establish: Issued state authorization or final construction sheets

Source link

Beach Project Act application index

Town; Jan 2025 application era

Establishes: State application and supporting materials

Does not establish: Issuance date, recorded line for a particular parcel

Source link

March 6 joint meeting notice

ADCNR/ADEM; 2025-02-04

Establishes: Meeting on pending state application

Does not establish: Approval

Source link

October 2024 and December 2024 presentations

Town; 2024-10-16 and 2024-12-11

Establishes: Early design and hearing process

Does not establish: Current final dimensions or current funding

Source link

Fact sheets 1–6 and FAQ

Town; 2022–summer 2025

Establishes: Development history and owner's questions

Does not establish: Current funding/permit status where superseded

Source link

Owner process letter

Town; older/undated letter referencing December hearing

Establishes: Town's description of designated line and perpetual easement rights

Does not establish: Executed deed text for any given owner

Source link

FY26 appropriations announcement

Sen. Katie Britt; 2026-01-21

Establishes: Separate $5m secured announcement and purpose

Does not establish: Its inclusion in the RESTORE budget or amount spent

Source link

Town bid-notices index

Town; checked 2026-09-28

Establishes: No West End listing observed in reviewed notices

Does not establish: Proof no other solicitation or unpublished procurement exists

Source link

NOT YET VERIFIED ONLINE

Complete issued USACE permit

NOT YET VERIFIED ONLINE

ADEM issued instrument

NOT YET VERIFIED ONLINE

Beach Act approval / recorded designated line

NOT YET VERIFIED ONLINE

POA recording instrument

NOT YET VERIFIED ONLINE

Final design

NOT YET VERIFIED ONLINE

West End bid solicitation (IFB/RFP)

NOT YET VERIFIED ONLINE

Award

NOT YET VERIFIED ONLINE

Contract

NOT YET VERIFIED ONLINE

Notice to proceed (NTP)

Update Log

2026-09-28 — Tracker baseline established

Tracker baseline established. Council-approved $38m implementation funding and December 8, 2025 USACE approval date documented; Town-reported state permits and POA easement labeled as attributed claims. Town easement snapshot dated August 24 and construction target winter 2027. No West End solicitation, award, NTP or construction evidence located in reviewed public sources. Initial version records unresolved funding reconciliation, issued state permit details and parcel easement counts as unknown. Sources: Town project and bid pages, RESTORE proposal and finding, ADCNR announcement, USACE notice.

Related Dauphin Island Coverage

Official Project Maps

Official project maps (Town)

Project footprint shown in official preliminary/permit materials; final design and parcel treatment may change.

View official maps

USACE public notice — borrow areas and pipeline corridor

Offshore borrow-area and proposed pipeline overview — proposed/permitted, not an as-built route.

View USACE notice

Town easement map (August 24, 2026 snapshot)

Town's August 24, 2026 four-sheet easement snapshot — not a current deed record.

View easement map