Duluth, Georgia Development & Zoning Tracker

What is proposed, what has been approved and what is actually being built are different questions. This tracker follows selected Duluth land-use cases and links the records behind each finding. It separates zoning decisions, permits and physical construction so that an approved housing limit is never presented as a count of homes built.

The inventory covers major and selected secondary city cases from 2024 through the research cutoff, plus a separate regional-review proposal and public/contextual records. It is not a complete census of active permits. Some parcel relationships, final plans and construction records remain unresolved. Those gaps are visible below.

Start here: 77-townhome Buford/Peachtree case · Portman regional review · Case inventory · Public and boundary context · Questions and answers

What the records establish

Buford/Peachtree

Maximum 77 townhomes approved with conditions; permits and construction commencement not established.

Portman / DRI 4748

Approximately 1,400 homes proposed in regional review; local approval not located.

Foundry

Approved ceiling of 320 apartments, a net increase of 64 over 256 existing units; finished conversions unknown.

Bunten Road Park

Dated official updates establish construction work; projected reopening and completion dates are not confirmation of completion.

How to read a status

Land use tells you what a public body decided. Permits tell you whether a particular scope of work has a documented permit. Construction tells you whether physical work has been established by dated evidence. "Unknown" describes an unestablished fact. "Not located" describes a missing record in this research; it does not mean the record does not exist.

A Planning Commission recommendation is distinct from a Council decision. A motion can also table or withdraw a case. Draft minutes remain labeled draft. A regional-review file marked certified complete is not a completed development.

For disputes involving a court case, see how court rulings, settlements and permits differ.

Buford Highway / Peachtree Road: the 77-townhome case

Case Z2025-001 · Council conditional approval, August 11, 2025 · Permit state: unknown · Construction state: unknown.

Duluth City Council approved a PUD for a maximum of 77 townhomes at Buford Highway and Peachtree Road on August 11, 2025, by a 5–0 vote. Conditions include a minimum of 2,200 heated square feet per home and road, drainage, design and maintenance obligations. The published Council minutes are labeled draft. Project-specific permits, construction commencement and completed homes were not established in the reviewed records.

Embry Development Company LLC is the applicant; staff lists multiple owners. The request changes HC-A/HC-R zoning to PUD for attached single-family homes. The staff cover identifies ten addresses and eleven parcels. Address and parcel transcriptions differ in parts of the record, so the source list is preserved pending reconciliation rather than treated as a verified map boundary.

Staff-cover addresses: 3375 Buford Hwy; 3355 Buford Hwy; 3366 Buford Hwy; 3356 Peachtree Rd; 3346 Peachtree Rd; 3305 Peachtree Rd; 3357 Peachtree Rd; 3337 Peachtree Rd; 3307 Buford Hwy; 3435 Davenport Rd.

Staff-cover parcels: R6292 065, R6292 043, R6292 043A, R6292 057, R6292 042, R6292 069, R6292 041, R6292 049, R6292 056, R6292 050, R6293 644.

Decision timeline

DateRecord and actionWhat it establishes
2025-02-28Applicant letter proposes 77 homesEarly concept; not a filing receipt or permit
2025-05-05PC postpones caseNo approval at this meeting
2025-07-07PC recommends approval with conditions, 4–0Advisory action; heading says 76, discussion says 77
2025-08-11Council approves R2025-10, 5–0Separate Peachtree Road abandonment/exchange action
2025-08-11Council approves O2025-33 with conditions, 5–0Maximum 77 homes; Council minutes published as draft
2026-09-29Through September 29, 2026: Later permits and official physical-work evidence not establishedConstruction and completion remain unknown

Councilmembers Harkness, Thomas, Doss, Graeder and Cummings voted in favor. Graeder moved approval and Doss seconded. An executed standalone ordinance was not separately retrieved.

Approved limits, plans and source conflicts

The approved conditions specify a maximum of 77 townhomes and a minimum of 2,200 heated square feet per home. Earlier applicant descriptions of 1,500–2,000 square feet do not replace the later minimum. The concept plan is at PDF page 62 of the August packet, followed by an illustrative plan at page 63 and elevations from page 64. These are zoning exhibits; a final stamped construction set and its revision date were not established.

The staff cover gives approximately 6.12 acres, while the density discussion uses 6.21 acres and 12.39 units per acre. These conflicting values remain attributed to their sources. The tracker does not present a reconciled exact acreage or density. The July PC heading's 76-home figure also remains visible, even though the later Council condition establishes the approved maximum of 77.

Roads and obligations

R2025-10 concerns approximately 0.593 acre, or 25,846 square feet, of Peachtree Road. The exchange contemplates Embry constructing and dedicating a new public roadway while preserving existing utility easements. Internal private roads and drainage have separate maintenance obligations. The road action is not evidence that an exchange deed was recorded, a road was built or the city accepted it.

The concept depicts circulation, sidewalks, a Davenport connection and underground stormwater treatment. A standalone traffic study, approved drainage calculations and utility-capacity approval were not located. Discussion of anticipated trip reduction is planning analysis, not a measured traffic result.

Condition groupRequired obligationCompliance evidence
1–4: Recorded plat and maintenance noticesConditions must appear on the final plat; obligations survive ownership; private roads and drainage have maintenance and purchaser-notice obligations.Not established
5–6: HOA and rental restrictionsHOA covenants before building permits; maximum 10% rented/leased and maximum 5% initial non-owner-occupant sales.Not established
7–8: Utilities and concept conformityUnderground utilities and screened equipment; concept and exhibits remain subject to the adopted conditions.Not established
9–11: Housing ceiling and standardsMaximum 77 townhomes; minimum 2,200 heated square feet; applicable UDC standards.Not established
12–16: Architecture, garages and site detailsArchitectural/material requirements, two-car garages, driveway standards, retaining-wall permitting and equipment screening.Not established
17: LightingLighting approval required before the development permit.Not established
18–19: Fence and landscapingDecorative fence/pillars and enhanced Buford/Davenport landscaping; plan approval required before development permit.Not established
20–22: Signs, cleanup and maintenanceSign plan before building permits, trash removal before certificate of occupancy and ongoing maintenance.Not established

These summaries explain the source conditions; the adopted legal text and incorporated exhibits control. Recorded plats/covenants, permit-stage plans and inspection/occupancy evidence are still needed to establish compliance.

Buford source record: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT; PC SIGNED MINS 5-5-25.pdf; 7-7-25 PC SIGNED MINS.pdf

Portman at McClure Bridge Road: separate regional review

DRI 4748 · Regional completeness certified September 10, 2026 · Local Council approval not located.

Portman Holdings proposed approximately 1,400 homes, 80,000 square feet of commercial space and 100,000 square feet of medical office space at 3554 McClure Bridge Road. DRI 4748 was certified complete for regional review on September 10, 2026. A local Council approval and approved housing maximum were not located. Certified complete does not mean the development is approved or built.

The initial filing identifies owner SHFF Duluth LLC, approximately 111.55 acres and parcels 6322 425 and 6322 003. Duluth is the submitting local government; the whole project footprint has not been independently checked against the city boundary. An exact residential unit-type breakdown and a local city case number were not established.

The initial DRI submission is dated May 27, 2026; additional information followed August 18. The summary gives October 10, 2026 as projected process completion. That is not a scheduled city hearing. The applicant's 2031 completion year is also a projection.

The additional form reports projected traffic of 12,622 daily trips, 981 AM-peak trips and 1,008 PM-peak trips. It references a Kimley-Horn study that was not retrieved. Surface/underground detention and a proposed southern-stream buffer/setback change appear in the proposal; final findings or permission for those changes were not established.

What remains unknown: local zoning decision, approved maximum, full traffic study and regional findings, final engineering, permits, start of construction and completion.

Regional-review source record: DCA DRI4748 summary; DCA initial form; DCA additional form

Case inventory

The following cards describe selected project records. Separate case filings and modifications are grouped with the property when the relationship is established. The two Peachtree Residential cases remain separate records with an unresolved relationship. No combined housing total is shown.

Buford Highway / Peachtree Road: the 77-townhome case

Z2025-001

Council approved (conditional)

Case Z2025-001 · Council conditional approval, August 11, 2025 · Permit state: unknown · Construction state: unknown.

See Buford/Peachtree section

Portman at McClure Bridge Road: separate regional review

DRI 4748

Regional review (local approval not located)

DRI 4748 · Regional completeness certified September 10, 2026 · Local Council approval not located.

See Portman regional review section

Futures Church / Providence townhomes

Z2024-001

Council approved (conditional)

Z2024-001 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: Old Peachtree Road and Sugarloaf Parkway

Housing: Approved desc: 71

Deciding body: Duluth City Council

3282 Davenport Road subdivision

Z2024-005MZ2025-001 (mod.)

Council approved (conditions modified)

Z2024-005 / MZ2025-001 · Council approved conditions modified

Land use

Council approved (conditions modified)

Permits

Unknown

Construction

Unknown

Addresses: 3282 Davenport Road

Housing: Approved max: 29

Deciding body: Duluth City Council

3407 Duluth Highway townhomes

Z2024-004

Council approved (conditional)

Z2024-004 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: 3407 Duluth Highway

Housing: Approved desc: 17

Deciding body: Duluth City Council

The Foundry apartment conversion

Z2025-002 (mod.)

Council approved (conditional)

Z2025-002 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Housing: Approved max: 320 · Existing: 256 · Net: +64

Deciding body: Duluth City Council

Peachtree Residential 28-townhome proposal

Unresolved
Z2025-004

Withdrawn

Z2025-004 · Withdrawn

Land use

Withdrawn

Permits

Unknown

Construction

Unknown

Addresses: 0 Peachtree Industrial Boulevard

Housing: Proposed: 28

Deciding body: Duluth Planning Commission

Peachtree Residential 20-townhome proposal

Unresolved
Z2026-005

Tabled

Z2026-005 · Tabled

Land use

Tabled

Permits

Unknown

Construction

Unknown

Addresses: 0 Peachtree Industrial Boulevard

Housing: Proposed: 20

Deciding body: Duluth Planning Commission

Forestar 138-townhome PUD modification

Unresolved
MZ2025-002 (mod.)

Modification withdrawn; underlying approval unresolved

Modification withdrawn; underlying PUD approval and property identity unresolved.

Land use

Modification withdrawn; underlying approval unresolved

Permits

Unknown

Construction

Unknown

Housing: Proposed: 138

Deciding body: Duluth Planning Commission

2641 North Berkeley Lake warehouse redevelopment

Z2026-001 (mod.)

Council approved (conditional)

Z2026-001 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: 2641 North Berkeley Lake Road

Housing: Unknown

Deciding body: Duluth City Council

Rainbow Village former ROW access parcel

Z2025-005

Council approved

Z2025-005 · Council approved

Land use

Council approved

Permits

Unknown

Construction

Unknown

Addresses: 3431 Duluth Highway; 3427 Duluth Highway

Housing: Unknown

Deciding body: Duluth City Council

Yi Hwang Academy middle school use

SU2026-002

Council approved (conditional)

SU2026-002 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: 4400 River Green Parkway

Housing: Unknown

Deciding body: Duluth City Council

River Green preschool and after-school

SU2025-002

Council approved (conditional)

SU2025-002 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: 4680 River Green Parkway

Housing: Unknown

Deciding body: Duluth City Council

Elevation Autism River Green suite

SU2024-005

Council approved

SU2024-005 · Council approved

Land use

Council approved

Permits

Unknown

Construction

Unknown

Addresses: 4375 River Green Parkway, Suite 150

Housing: Unknown

Deciding body: Duluth City Council

2516 Main Street Public Works annexation

A2024-002Z2024-006

Annexation and zoning approved

A2024-002 / Z2024-006 · Annexation and zoning approved

Land use

Annexation and zoning approved

Permits

Unknown

Construction

Unknown

Addresses: 2516 Main Street

Housing: Unknown

Deciding body: Duluth City Council

2407 Main Street Public Works expansion annexation

A2026-001Z2026-006

Annexation and zoning approved

A2026-001 / Z2026-006 · Annexation and zoning approved

Land use

Annexation and zoning approved

Permits

Unknown

Construction

Unknown

Addresses: 2407 Main Street; 2407 Chattahoochee Drive

Housing: Unknown

Deciding body: Duluth City Council

Duluth Community Center fitness/badminton variance

V2024-006

ZBA denied

V2024-006 · Zba denied

Land use

ZBA denied

Permits

Unknown

Construction

Unknown

Addresses: 3769 Rogers Bridge Road

Housing: Unknown

Deciding body: Duluth Zoning Board of Appeals

Pleasant Hill auto-inventory overflow parking

V2025-001

ZBA approved (conditional)

V2025-001 · Zba approved conditional

Land use

ZBA approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: 2493 Pleasant Hill Road

Housing: Unknown

Deciding body: Duluth Zoning Board of Appeals

2772 Buford Highway bank drive-through reuse

SU2025-003

Council approved (conditional)

SU2025-003 · Council approved conditional

Land use

Council approved (conditional)

Permits

Unknown

Construction

Unknown

Addresses: 2772 Buford Highway

Housing: Unknown

Deciding body: Duluth City Council

Buford Highway outdoor construction storage

SU2024-007

Council denied

SU2024-007 · Council denied

Land use

Council denied

Permits

Unknown

Construction

Unknown

Addresses: 3570-B Buford Highway, Suite 101

Housing: Unknown

Deciding body: Duluth City Council

3135 Buford Highway acquisition and demolition

Funding agreement approved

BA-FY26-04 / City–URA IGA · Funding agreement approved

Land use

Funding agreement approved

Permits

Unknown

Construction

Unknown

Addresses: 3135 Buford Highway

Housing: Unknown

Deciding body: Duluth City Council

Legislative annexation implementing zoning

Z2024-002

Implementing zoning approved

Legislative annexation implementing zoning

See public and boundary context

Norfolk Southern railroad zoning alignment

Z2024-003

Council approved

Norfolk Southern railroad zoning alignment

See public and boundary context

Bunten Road Park walking trail and park improvements

Not applicable (capital work record)

Bunten Road Park walking trail and park improvements

See public and boundary context

Public and boundary context

These records are separate from the private-development inventory. Annexation/zoning programs are not new housing projects.

Legislative annexation implementing zoning

Z2024-002

Implementing zoning approved

Legislative annexation implementing zoning

Land use

Implementing zoning approved

Permits

Unknown

Construction

Unknown

Housing: Unknown

Deciding body: Duluth City Council

Norfolk Southern railroad zoning alignment

Z2024-003

Council approved

Norfolk Southern railroad zoning alignment

Land use

Council approved

Permits

Unknown

Construction

Unknown

Housing: Unknown

Deciding body: Duluth City Council

Bunten Road Park walking trail and park improvements

Not applicable (capital work record)

Bunten Road Park walking trail and park improvements

Land use

Not applicable (capital work record)

Permits

Unknown

Construction

Physical work documented

Housing: Unknown

Deciding body: City of Duluth project update

Housing figures: approved does not mean built

RecordProposed or described unitsExplicit approved maximumPermittedUnder constructionCompleted
Buford/Peachtree77; one PC heading says 7677UnknownUnknownUnknown
Futures/Providence71 in approved project descriptionExecuted maximum clause not separately establishedUnknownUnknownUnknown
ANM, Duluth Highway17 in approved project descriptionExecuted maximum clause not separately establishedUnknownUnknownUnknown
Davenport29 detached29UnknownUnknownUnknown
Foundry256 existing → 320 after conversion320 total; net +64UnknownUnknownUnknown
Peachtree Z2025-00428, withdrawnNot establishedUnknownUnknownUnknown
Peachtree Z2026-00520, tabledNot establishedUnknownUnknownUnknown
Forestar MZ2025-002138 in withdrawn modificationUnderlying approval unresolvedUnknownUnknownUnknown
Portman DRI 4748Approximately 1,400 proposedNot locatedUnknownUnknownUnknown

Location and coverage

A Duluth postal address does not establish city jurisdiction. City proceedings identify the authority acting on the cases in this inventory; legal parcel boundaries and recent annexations require separate location checks. No parcel map is published from this seed dataset because its coordinates and geometry have not been verified.

Map locations have not yet been verified.

Historical projects such as Marlowe, Encore, Evanshire and Riversong need a carryover check before their current construction status can be stated. The city's public project page is not a complete permit inventory, and this tracker is not one either. A missing entry should not be read as evidence of no activity.

Upcoming hearings

No future case hearing verified for this release.

A tabled case remains tabled until a later record establishes rescheduling. Projected regional-review dates are not placed on the hearing calendar.

Questions and answers

What is proposed or approved in Duluth, Georgia?

This tracker covers selected city land-use records, a separate regional-review proposal and public/contextual projects. Buford/Peachtree, Davenport and the Foundry have Council approvals with conditions. Portman’s roughly 1,400-home proposal is in regional review in the located record. These are different stages, not a combined count of homes being built.

Sources: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT; PC SIGNED MINS 5-5-25.pdf; 7-7-25 PC SIGNED MINS.pdf; DCA DRI4748 summary; DCA initial form; DCA additional form; DuluthAgendaBinder3-10-25 (r).pdfDRAFT; DuluthAgendaBinder4-14-251.pdfDRAFT

Was the 77-townhome Buford Highway/Peachtree Road project approved?

Yes. Council approved O2025-33 with conditions on August 11, 2025, by 5–0. The conditions retain a maximum of 77 townhomes and require at least 2,200 heated square feet per home. The published Council minutes are labeled draft. Permits and construction commencement were not established.

Sources: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT; PC SIGNED MINS 5-5-25.pdf; 7-7-25 PC SIGNED MINS.pdf

Why does one Buford record say 76 homes?

The July 7, 2025 Planning Commission minutes use 76 in the request heading and 77 in the discussion. Later Council conditions specify a maximum of 77. The tracker preserves the earlier discrepancy and uses the final condition for the approved ceiling.

Sources: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT; PC SIGNED MINS 5-5-25.pdf; 7-7-25 PC SIGNED MINS.pdf

Are Portman’s 1,400 homes approved?

A local Council approval was not located. DRI 4748 was certified complete for regional review on September 10, 2026. That status concerns the review submission. It does not approve construction or establish a final housing limit. October 10, 2026 is a projected process-completion date, not a verified city hearing.

Sources: DCA DRI4748 summary; DCA initial form; DCA additional form

How many apartments does the Foundry approval add?

The approved conversion increases the approved housing ceiling from 256 existing apartments to 320, a net increase of 64. It converts 64 three-bedroom units into 128 one-bedroom units. The number actually permitted or converted was not established.

Sources: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT

Are the 28-home and 20-home Peachtree proposals approved?

No approval was established for either case. Z2025-004 was withdrawn on December 1, 2025. Z2026-005 was tabled until further notice on July 6, 2026. Their exact site relationship remains unresolved, so they are not summed as 48 homes or presented as a verified revision.

Sources: 12-1-25 PC SIGNED MINS.pdf; 7-6-26 SIGNED MINS PC.pdf

Which projects have verified construction activity?

The official Bunten Road Park updates establish construction activity, including March 30, 2026 mobilization. For the private-case work in this tracker, construction progress was not established. Unknown does not mean a project is unbuilt, inactive or stalled.

Sources: Bunten Road Park project updates

Does rezoning mean building can begin?

A zoning decision establishes the allowed use and conditions documented in that decision. Buford’s conditions explicitly require later approvals before development or building permits and before occupancy. The decision itself is not evidence that those permits have been issued.

Sources: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT; PC SIGNED MINS 5-5-25.pdf; 7-7-25 PC SIGNED MINS.pdf

Is a Duluth mailing address inside Duluth city limits?

Not necessarily. This tracker uses city proceedings and parcel identifiers to identify the authority acting on a case. Boundary geometry remains unverified for these seed records. Annexation cases have separate jurisdiction histories, and the full Portman footprint needs a boundary check.

Sources: DCA DRI4748 summary; DCA initial form; DCA additional form; DuluthAgendaBinder1-13-25.pdf; 1-13-25 M&C SIGNED MINS.pdf; DuluthAgendaBinder7-13-26.pdf; DuluthAgendaBinder8-10-26.pdfDRAFT

Did the Davenport modification approve more homes?

No additional 29-home project is established by MZ2025-001. It modifies conditions of Z2024-005, including the Hall Circle ADA trail obligation. The approved maximum remains 29 detached homes.

Sources: DuluthAgendaBinder3-10-25 (r).pdfDRAFT; DuluthAgendaBinder4-14-251.pdfDRAFT; DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT

Where can I see the site plans and conditions?

The Buford concept is in the August 11, 2025 Council packet at PDF page 62, followed by an illustrative plan at page 63. Conditions are at pages 54–57. These are zoning exhibits; a final stamped construction plan was not located. Each case below links its own records.

Sources: DuluthAgendaBinder8-11-25.pdf; 8-11-25 draft minKM.pdfDRAFT; PC SIGNED MINS 5-5-25.pdf; 7-7-25 PC SIGNED MINS.pdf

Does not located mean a permit or appeal does not exist?

No. It means the reviewed public sources did not establish that record. The research did not recover a complete permit ledger or clear every court docket. Permit, appeal and construction fields stay unknown until project-specific evidence supports a change.

Source library

30 distinct source URLs. Each card links the exact supplied URL with publisher, format, publication status, and retrieved date. PDF positions are file-page indices, not necessarily the printed page numbers.

DuluthAgendaBinder8-11-25.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

8-11-25 draft minKM.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Draft · Retrieved: 2026-09-29

Source link

PC SIGNED MINS 5-5-25.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

7-7-25 PC SIGNED MINS.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

DCA DRI4748 summary

Publisher: Georgia DCA · Format: html

Publication status: Not established · Retrieved: 2026-09-29

Source link

DCA initial form

Publisher: Georgia DCA · Format: html

Publication status: Not established · Retrieved: 2026-09-29

Source link

DCA additional form

Publisher: Georgia DCA · Format: html

Publication status: Not established · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder6-10-24.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder7-8-24.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder3-10-25 (r).pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder4-14-251.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinderComp2-10-24.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

12-1-25 PC SIGNED MINS.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

7-6-26 SIGNED MINS PC.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

10-6-25 PLAN COMM SIGNED MINS.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder5-11-26.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

M&C 5-11-26 signed mins.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder12-8-25.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

12-8-25 draft min.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Draft · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder7-13-26.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder8-10-26.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder9-8-25.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder10-13-25compDER.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder1-13-25.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

1-13-25 M&C SIGNED MINS.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder5-13-24.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder10-14-24.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Not established · Retrieved: 2026-09-29

Source link

DuluthAgendaBinder11-11-24.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Packet contains draft material · Retrieved: 2026-09-29

Source link

03-26-25 - ZBA SIGNED MINS.pdf

Publisher: City of Duluth · Format: pdf

Publication status: Signed · Retrieved: 2026-09-29

Source link

Bunten Road Park project updates

Publisher: City of Duluth · Format: html

Publication status: Not established · Retrieved: 2026-09-29

Source link

About these records

WorthFighting prepared this tracker from official materials reviewed through September 29, 2026. Exact document links and PDF page positions are supplied so readers can inspect the evidence. Some Council records remain published as draft minutes. The research did not recover a complete issued-permit/inspection/occupancy dataset or perform comprehensive appeal-docket clearance.

Update log — September 29, 2026: Initial production dataset prepared from the completed research. The Bunten field card is accounted for separately, case modifications are linked to their parent records where established, and unknown permits and physical progress remain explicit. No later governmental action is implied by this editorial preparation.